While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report: * Approved Work Package Cost Estimates: US$9,500 * Contingency reserves: $500 % * Management reserves: 10% of contingency reserves * Percent complete of the project: 50% * Planned percent of the project: 40% * Actual costs of the project: US$4,500 What is accurate about the project status?
Correct Answer: D
Recent Comments (The most recent comments are at the top.)
Ciccio - Jun 01, 2022
Hi Guy Martin As the 4 possible answers are expressed in %, my understanding is the answers are related to CPI and SPI, not to CV and SV A CPI value greater than 1.0 indicates a cost underrun of performance to date. You are right. But using your numbers, CPI will be 1.111 (11%) instead of 1.1 (10%) CPI = EV/AC = 5000/4500 = 1,1111 There are no possible answers with 11% This is why, we have to calculate the SPI and to use the PV SPI=EV/PV
Guy Martin - May 30, 2022
The cost baseline is the cost of the project. It will include all the costs of all the deliverables on the project. The cost baseline is what will be included in the project management plan and will be used to measure the performance of the project once it is executed. This is alsoknown as the budget at completion (BAC). A.R book so BAC= The cost baseline= cost estimates+ contingency reserves=9,500+0,500=10,000. EV=50%*BAC=5,000 AC=4,500 CV=5000-4500=500 so the projet is cost 500 lower than 5000 (10% lower) Don't use PV (this is misinformation) . Costs are always compared to the earned value.
Ciccio - May 12, 2022
The correct answer will be C AC = $4500 CPI = EV/AC = 4750/4500= 1,05 The project cost is 5% higher than planned.
Tofahel Chowdhury - Apr 23, 2022
The correct answer will be C EV = $9500*50%=$4750 PV = $9500*40%=$3600 SPI = ($4750/$3600)=1.25, so actual work is more than 25% of the planned work
Recent Comments (The most recent comments are at the top.)
Hi Guy Martin
As the 4 possible answers are expressed in %, my understanding is the answers are related to CPI and SPI, not to CV and SV
A CPI value greater than 1.0 indicates a cost underrun of performance to date. You are right.
But using your numbers, CPI will be 1.111 (11%) instead of 1.1 (10%)
CPI = EV/AC = 5000/4500 = 1,1111
There are no possible answers with 11%
This is why, we have to calculate the SPI and to use the PV
SPI=EV/PV
The cost baseline is the cost of the project. It will include all the costs of all the deliverables on the project. The cost baseline is what will be included in the project management plan and will be used to measure the performance of the project once it is executed. This is alsoknown as the budget at completion (BAC). A.R book so
BAC= The cost baseline= cost estimates+ contingency reserves=9,500+0,500=10,000.
EV=50%*BAC=5,000
AC=4,500
CV=5000-4500=500 so the projet is cost 500 lower than 5000 (10% lower)
Don't use PV (this is misinformation) . Costs are always compared to the earned value.
The correct answer will be C
AC = $4500
CPI = EV/AC = 4750/4500= 1,05
The project cost is 5% higher than planned.
The correct answer will be C
EV = $9500*50%=$4750
PV = $9500*40%=$3600
SPI = ($4750/$3600)=1.25, so actual work is more than 25% of the planned work