Valid PMP Dumps shared by EduDump.com for Helping Passing PMP Exam! EduDump.com now offer the newest PMP exam dumps, the EduDump.com PMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMP dumps with Test Engine here:
While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report: * Approved Work Package Cost Estimates: US$9,500 * Contingency reserves: $500 % * Management reserves: 10% of contingency reserves * Percent complete of the project: 50% * Planned percent of the project: 40% * Actual costs of the project: US$4,500 What is accurate about the project status?