<< Prev Question Next Question >>

Question 68/161

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (161q)
Question 1: A project manager is in the middle of an agile project compr...
Question 2: During the course of a project the project manager's immedia...
Question 3: Experienced team members assigned to a critical project are ...
Question 4: Drag the organizational characteristics on the left to the c...
1 commentQuestion 5: An agile project is in its eighth iteration out of 16 After ...
Question 6: The product owner decides to launch a product after a couple...
Question 7: A project manager is using a hybrid approach for project del...
Question 8: During an iteration demo, a customer noticed an enhancement ...
Question 9: During the implementation stage of a project. a newly appoin...
Question 10: During the course of a project, the team develops negative g...
Question 11: local company is developing a new product and. for the first...
Question 12: A project manager is assigned to oversee the deployment of a...
Question 13: During an inspection, the production phase was stopped becau...
Question 14: A company's CEO has just returned from a conference on the u...
1 commentQuestion 15: A senior management team member contacts an agile project le...
Question 16: A project manager is managing a project with a hybrid approa...
Question 17: During the initiation stage of a multimedia exhibition-desig...
Question 18: During an iteration of a project, a planned activity becomes...
Question 19: At the end of a meeting a functional manager takes the proje...
Question 20: A senior business stakeholder with many years of experience ...
Question 21: An integrated project involves the interaction of both hardw...
Question 22: During a meeting to define project scope a stakeholder tells...
Question 23: Due to a company merger and acquisition process, the main st...
Question 24: A project manager is assigned to a new project. The project ...
Question 25: An agile project is running activities to define the minimum...
Question 26: A project manager is worried that a key stakeholder is not p...
Question 27: A company is using a predictive approach for the development...
Question 28: After a project has been approved, a key stakeholder tells t...
Question 29: A project manager created a contingency plan associated with...
Question 30: A year after implementing a policy change to improve diversi...
Question 31: Important projects in the portfolio backlog need to be deliv...
Question 32: A project manager is assigned to a project that is in develo...
Question 33: A large multi-year project requires highly skilled staff for...
Question 34: A project manager has received an updated earned value analy...
Question 35: A self-organizing team was delivering as committed. The team...
Question 36: A project manager is assigned to a new marketing campaign Th...
Question 37: A project team member complained to the project manager that...
Question 38: A company is changing their current business model The chang...
Question 39: A project manager for a maintenance project has a contract t...
Question 40: A project is being executed The project's life cycle is defi...
Question 41: A company is planning a digitization project. Which action s...
Question 42: The project manager is having difficulty communicating with ...
Question 43: A global company hired a project manager for a new implement...
Question 44: A project manager has two projects that are being executed a...
Question 45: The project sponsor on an agile project informed the project...
Question 46: In an agile project, the project manager notices that one te...
Question 47: A project manager for a government organization often deals ...
Question 48: A project manager Is transitioning from a predictive We cycl...
Question 49: Which two actions should a project manager consider while la...
Question 50: The change control board (CCB) rejects a change request subm...
Question 51: While managing a project, the project manager has just notic...
Question 52: In a multinational project, stakeholders are in different ti...
1 commentQuestion 53: The portfolio management office wants to cut costs by suspen...
Question 54: During the third iteration, the team encounters a major dela...
Question 55: A project manager has team members around the world in many ...
Question 56: A stakeholder is requesting that the project manager share p...
Question 57: A project is nearing completion The contingency time has bee...
Question 58: A team has been struggling with various issues during the co...
1 commentQuestion 59: An operations manager continuously raises concerns about a p...
Question 60: The project manager of a hybrid project learns that a stakeh...
1 commentQuestion 61: A project manager has been using predictive methodology for ...
Question 62: In a time-critical construction project, a misunderstanding ...
Question 63: A project just kicked off and management's expectation is to...
Question 64: The project team finds that the latest delivery from a vendo...
Question 65: Development team members are located in three different time...
Question 66: After a project team has been working on a project for sever...
Question 67: As part of a temporary assignment, a project manager is lead...
Question 68: A new agile team is having trouble completing tasks. There a...
Question 69: A project manager is assigned to a project within a program....
Question 70: One of a project manager's team members is continuously impr...
Question 71: During the design phase of a project the project manager not...
Question 72: A research and development team is finishing up a two year i...
Question 73: A vendor informed the project manager that a critical resour...
Question 74: A company wants to increase the commercial value of one of i...
Question 75: During a daily standup meeting, a roadblock was raised that ...
Question 76: A high-performing team member's performance has been consist...
Question 77: for a project has reported the potential for a delivery dela...
Question 78: A Scrum team has committed to delivering a specific capabili...
Question 79: A project manager is assigned to a strategic communication p...
Question 80: During project execution, a project manager is informed that...
Question 81: A supplier was supposed to mobilize a government-issued, lic...
Question 82: During the execution phase of a project a new project manage...
Question 83: A technical subject matter expert (SME) identifies an occurr...
Question 84: A new team member on a self-organizing team is finding it di...
Question 85: While reviewing prototypes, the quality team found some devi...
Question 86: A verbal announcement is made that the new team member joini...
Question 87: Project A is critical for the company and must be completed ...
Question 88: A project manager has noticed that the performance of a new ...
1 commentQuestion 89: A company starts implementing Scrum About halfway through th...
Question 90: A project is delayed due to multiple problems discovered dur...
Question 91: Two functional managers disagree on key features of one deli...
Question 92: Team members are having a discussion with the project manage...
Question 93: The programming activities of a project were planned to last...
1 commentQuestion 94: A company is transitioning from a predictive to agile delive...
Question 95: A project manager is assigned to a technical research projec...
Question 96: An agile project is starting and the assigned team is new to...
Question 97: An intern is replacing a critical resource midway through a ...
Question 98: A highly skilled team resource received a job offer and is l...
Question 99: A project manager is working on a major construction project...
Question 100: A project manager has been managing a highly complex project...
Question 101: A project manager has been asked to participate in the procu...
Question 102: One of the main inputs required for a deliverable is missing...
Question 103: A large company has agreed on a business case for an environ...
Question 104: In an advanced stage of a project a stakeholder who is not r...
Question 105: After a project learn has been working on a project for seve...
Question 106: When reviewing the project team's performance the project ma...
Question 107: An agile project team is building a new product. The stakeho...
Question 108: A project manager presented the project schedule to the mam ...
Question 109: A global petroleum crisis has affected the distribution of c...
Question 110: A company is moving its headquarters to another city. The pr...
Question 111: A new team member has joined an agile project, replacing a t...
Question 112: A company that is introducing a new product into the market ...
Question 113: A project manager who is managing a critical project in a mu...
Question 114: A project manager is struggling to figure out the performanc...
Question 115: A project manager has been assigned to take over an existing...
Question 116: A labor union contract negotiation is delaying the completio...
Question 117: In a hybrid project, the customer decided on a major change ...
Question 118: In a fixed time and budget project the customer wants the de...
Question 119: An organization is transitioning to agile and a project has ...
Question 120: A project is behind schedule and over budget, resulting in a...
Question 121: The project manager has recently received funding approval f...
Question 122: Due to a recent budget reduction, two team members were rele...
Question 123: A project has a very tight delivery schedule The project is ...
1 commentQuestion 124: Close to the end of a project, a customer claims that some d...
Question 125: A company that is heavily focused on delivering projects usi...
Question 126: After reviewing the project management plan with key stakeho...
Question 127: A company has a lot of experience with predictive projects T...
Question 128: A project manager at a company is considering a high-perform...
Question 129: A project manager is assigned to a project in a company that...
Question 130: During a retrospective meeting a project manager hears that ...
Question 131: During the course of a project, the project manager wants to...
Question 132: Since the beginning of a project, the product owner keeps as...
Question 133: The team architect resigned from the company. The new archit...
Question 134: In a project management team meeting, one of the team member...
Question 135: A company has been following a predictive approach and alway...
Question 136: The tables show the requirements for an agile project with t...
Question 137: A company Is helping their client launch an Innovative produ...
Question 138: At the closing phase of the project the project manager send...
Question 139: A project manager is managing a project to develop a new too...
Question 140: The project manager has finished all the tasks of the projec...
Question 141: A project manager receives an update that the development fl...
Question 142: A project manager is managing a complex research project wit...
Question 143: A project manager is managing a hybrid project After attendi...
Question 144: A project team is conducting a retrospective. The team wants...
Question 145: The project is delayed due to the high amount of major chang...
Question 146: An organization has historically executed most projects usin...
Question 147: A project to develop a large hydropower plant is in the impl...
Question 148: A technical manager newly appointed by the client, visits th...
Question 149: The project manager of an agile project has been asked to re...
Question 150: During daily calls team members share task progress One team...
1 commentQuestion 151: During a documentation audit of an international company it ...
Question 152: A project manager is leading a meeting with key stakeholders...
Question 153: The business manager and the product owner are requesting a ...
Question 154: During the execution of a project the project manager notice...
Question 155: A team member is hosting an event and invites several collea...
Question 156: A project manager works with a global virtual team. The team...
Question 157: During the review of a project's list of deliverables, one o...
Question 158: A new project manager is planning an information security pr...
Question 159: A project is delayed due to an undelivered component, which ...
Question 160: A global company is executing a strategic project to upgrade...
Question 161: An agile project team discovers that they are unable to impl...