A project is proceeding less quickly than planned and most stakeholders complain about communication challenges The project manager has sufficient reserves to improve communications, and the team agrees it will positively impact the project Since approved reserves are already available, the team believes that a change request, which takes several days for approval, may not be required What should the project manager do?