<< Prev Question Next Question >>

Question 13/180

A successful project manager joins a strategic project with top talent from multiple departments. However, these high-performing team members experience constant distractions from their functional managers, which impacts quality and productivity.
What should the project manager do to get the team back on track?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (180q)
Question 1: A project manager receives an approved request related to a ...
Question 2: A senior executive, who has not been identified as a stakeho...
Question 3: An organization is entering into a major R&amp;D healthcare ...
Question 4: A project manager delivered the final project report and is ...
Question 5: A project manager in a weak-matrix environment must coordina...
Question 6: A project manager has been receiving enhancements to a produ...
Question 7: A project manager identifies a new project task that will no...
Question 8: While reviewing signed project documentation, the project ma...
Question 9: Before disbanding a project team, the project manager facili...
Question 10: A project manager leading a new project at a large corporati...
Question 11: A project team identifies the top four risks in a project, a...
Question 12: A product Installed early in a project is the incorrect size...
Question 13: A successful project manager joins a strategic project with ...
Question 14: A project sponsor decides to add a feature to the project th...
Question 15: After completing a project schedule, the project manager lea...
Question 16: A project is running on time, but the customer now requests ...
Question 17: A project manager is receiving new scope demands from multip...
1 commentQuestion 18: An external provider is late with the delivery of a finished...
Question 19: A project management office (PMO) asks a project manager to ...
Question 20: During testing of a project component a senior tester discov...
Question 21: A vendor submits a high-level project schedule for a three-y...
Question 22: A client asks a global IT company to develop a supply-chain ...
Question 23: A project is being audited to ensure compliance with organiz...
Question 24: A vendor ships a material four working days ahead of the act...
Question 25: During the project initiation phase, The project manager is ...
Question 26: A project team conducts acceptance testing of equipment agai...
Question 27: An IT group rejects a project deliverable citing noncomplian...
Question 28: A project manager creates an internet project repository ava...
Question 29: A set of high-impact repetitive tasks must be executed durin...
Question 30: A new project stakeholder is identified who has interest in,...
Question 31: A company has recurring quality issues with one of its sole-...
Question 32: A team member is working the required hours, but is deliveri...
Question 33: A project manager in a matrix organization notices that a re...
Question 34: After completion of a project's first deliverable, a stakeho...
Question 35: A matrixed organization has a history of project schedule an...
Question 36: During protect execution, a high-performing team member leav...
Question 37: A project is initiated to deliver a new version of an existi...
Question 38: A project's stakeholders include business unit executives, a...
Question 39: A project manager receives a request for proposal (RFP) and ...
Question 40: A project manager is working onsite daily with the client's ...
Question 41: A stakeholder instructs a propel manager 10 transfer a key r...
Question 42: A project manager conducted interviews and brainstorming wor...
Question 43: A senior manager asks a loam member for a quick update on th...
Question 44: During the next monthly meeting, a project manager wants to ...
Question 45: A new project manager joins a project in progress. The proje...
Question 46: A project team implemented an approved change, but this chan...
Question 47: A project manager begins the estimating process for a new pr...
Question 48: A global technology company invested in an infrastructure up...
Question 49: While working on a project, the project manager realizes tha...
Question 50: Provisional training is provided for a project that is in th...
Question 51: A design protect is ready to be transferred to production. W...
Question 52: A complex project is closing and many project team members r...
Question 53: A project manager in a Cross-functional organization needs t...
Question 54: A resource's functional manager requests confidential inform...
Question 55: A project manager wants to recruit another team member to re...
Question 56: After a functional team delivers a product the project manag...
Question 57: A few weeks after joining a multi-generational project learn...
Question 58: A project manager realizes that there is an inconsistency in...
Question 59: The project team needs to get additional data available in t...
Question 60: During the execution of a project, a key stakeholder asks th...
Question 61: During the end of a Critical project's execution phase, a pr...
Question 62: A project team is using agile methodologies 10 develop a com...
1 commentQuestion 63: One /ear into a five-year project, the project manager reali...
Question 64: Midway through project implementation, stakeholders lose con...
Question 65: A large risk to a project is identified and the risk managem...
Question 66: Prior to the implementation of a system upgrade, a team memb...
Question 67: An experienced project manager joins a project that has been...
Question 68: A project manager is managing a two-year agile project with ...
Question 69: A team of experts provides a project manager with different ...
Question 70: A performance report indicates a variation in a product's sp...
Question 71: During an IT solution implementation project, the sponsor bl...
Question 72: During a project's initiation phase, 200 stakeholders are id...
Question 73: A project's original budget at completion (BAC) was calculat...
Question 74: Following a company reorganization, a team member now report...
Question 75: A project manager learns there are several unexpected issues...
Question 76: A protect manager develops a business case during project in...
Question 77: The procurement department submits a request for proposal (D...
Question 78: In a multi-site development project, sharing documents withi...
Question 79: After reviewing work performance information, the project ma...
Question 80: A project's most recent status report indicates a schedule p...
Question 81: A project manager has two projects of equal, strategic organ...
Question 82: Due to a product's high importance, the sponsor wants to clo...
Question 83: A project manager implements an information system for a fin...
Question 84: A performing organization is consulted to implement a supply...
Question 85: During a project's final phase, the project manager evaluate...
Question 86: During a kick-off meeting a key stakeholder asks why one of ...
1 commentQuestion 87: A company wants to design and build its first robotic produc...
Question 88: A local supplier is unable to meet a delivery date. The proj...
Question 89: A project manager must obtain approval for a network cabling...
Question 90: After preparation of the project management plan, the projec...
Question 91: At the first team meeting, the project manager uses the risk...
Question 92: A project manager develops a project's risk breakdown struct...
Question 93: During a status meeting, a stakeholder requests a new requir...
Question 94: A natural disaster occurs that severely disrupts a project's...
Question 95: During the execution of a US$20 million project in a balance...
Question 96: During a status meeting with the customer, the project manag...
Question 97: A project team member discovered an issue with the system be...
Question 98: A project team member indicates that a change must be made t...
Question 99: During project execution, several concerned stakeholders con...
Question 100: A project manager is ready to start a new project that has a...
Question 101: While preparing for a product launch, the project manager co...
Question 102: A project manage identifies the root cause of a quality issu...
Question 103: A project manager is assign to start the charter of an IT pr...
Question 104: A project manager receives an approved change request relate...
Question 105: After performing a risk analysis, the project manager realiz...
Question 106: A project manager joins an ongoing firm fixed price (FFP) pr...
Question 107: Upon completion of a project cash-flow review, the project m...
Question 108: A software development protect lot a financial institution i...
Question 109: A project team is working on a project's new approved scope....
Question 110: Midway through a project, a subcontractor is replaced. The p...
Question 111: A new project manager resumes a project in its execution pha...
Question 112: An analysis during the design stage suggests that a project ...
Question 113: During a project steering committee meeting, the project man...
Question 114: A project manager must track schedule variances over time. W...
Question 115: A project manager is running a long-term project for a compa...
Question 116: An organization delivered a software package to three high-p...
Question 117: Because a project is behind schedule, the sponsor suggests r...
Question 118: A company is going through a reorganization Although not all...
Question 119: As a result of a new investor's participation stakeholders r...
Question 120: Due to increased price volatility a vendor asks the project ...
Question 121: To implement a customer relationship management (CRM) softwa...
Question 122: After presenting a prototype to the client, the project mana...
Question 123: A company is merging with another company, and some employee...
Question 124: Significant customer change requests to project scope result...
Question 125: A demanding project stakeholder insists that an additional f...
Question 126: As a project progresses the project manager notices that wee...
Question 127: During project execution, a project member informs the proje...
Question 128: A project manager is helping to draft a project because of t...
Question 129: During an IT hardware manufacturing project, the project man...
Question 130: All the deliverables defined in a project have been complete...
Question 131: To develop a new product, the project manager collects requi...
Question 132: A company's senior manager is expected to supply dedicated r...
Question 133: A project is in the execution phase. A risk management plan ...
Question 134: A project manager is implementing a project for a company's ...
Question 135: Stakeholders have conflicting opinions about whether a chang...
Question 136: An earthquake occurs at the site of a manufacturing plant co...
Question 137: A project manager is developing an organizational chart and ...
Question 138: Work on a project passes the customer acceptance test and th...
Question 139: A company has decided to create a project management office ...
Question 140: An issue requires the execution of the project's contingency...
Question 141: A customer is surprised about a change made to a deliverable...
Question 142: A system launched successfully and has been running smoothly...
Question 143: After reviewing an approved project's resource management pl...
Question 144: A client verbally approves the protect management plan What ...
Question 145: During a project review meeting, stakeholders disagree on th...
Question 146: Phase two of a complex, multi-phase project is completed, an...
Question 147: During a risk analysis of a new system's security features, ...
Question 148: After preparing the work breakdown structure (WBS), the proj...
Question 149: A project manager plans the agenda for a kick-off meeting As...
Question 150: While developing a propel schedule, the project manager iden...
Question 151: A project is in the closure phase, and most activities will ...
Question 152: After identifying a new risk, a project manager wants to det...
Question 153: A project manager is working on a building construction proj...
Question 154: A stakeholder identities an issue with which the project man...
Question 155: During project implementation, the project manager reviews i...
Question 156: A project manager is developing a schedule for a communicati...
Question 157: A client adds a new feature and requests a budget update the...
Question 158: During planning, a project team documented the possibility t...
Question 159: Four months into a one project, the customer requests a chan...
Question 160: A key project stakeholder requests that the project manageme...
Question 161: A project is using multiple vendors. What document should th...
Question 162: The implementation of a business requirement for an IT proje...
Question 163: A project manager suggests training a software development t...
Question 164: During a weekly status meeting, a team member informs the pr...
Question 165: An organization has contracts with an external supplier to s...
Question 166: A project manager needs to add a subject matter expert (SME)...
Question 167: A project's budgeted value of work completed is less than th...
Question 168: While developing the project charter stakeholders disagree a...
Question 169: During project execution, a protect team identifies new risk...
Question 170: At the completion of a project, customer agreement cannot be...
Question 171: What can a project manager do to communicate the formal proj...
Question 172: An approved change request adds an incentive to a lump sum c...
Question 173: A project manager completes a protect management plan for a ...
Question 174: A project is ready to complete the planning process, and all...
Question 175: A project team member identities a quality issue that may ca...
Question 176: A company has a longstanding client who is often late with p...
Question 177: A project manager identifies a risk for a complex module in ...
Question 178: A product manager needs a website to display product informa...
Question 179: During a project, several risks are identified. The project ...
Question 180: What information should a project manager request before dev...