An impact assessment reveals that a deliverable could delayed by two weeks. A key resource has not been available to work one a non-critical activity due to other priorities. This could cause work overload on the remaining resources. Since cost is a major constrain for this project, what should the project manager do immediately? Determine if the task has available float to meet the project end date.