<< Prev Question Next Question >>

Question 159/183

Continuous integration ensures that a product is:

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (183q)
Question 1: A product owner for two highly visible projects spends a gre...
Question 2: Agile team A struggles to deliver committed stories due to t...
Question 3: On a team new to Scrum, two team members are disrupting the ...
Question 4: Prioritize from high to low the sequence of User Story devel...
Question 5: The acronym for a good product backlog is DEEP. What does it...
Question 6: Which development mastery model of skill acquisition lies in...
Question 7: On a project using eXtreme Programming (XP), a customer test...
Question 8: What is the name of this facilitated process? One or more te...
Question 9: When the Agile team works in a single location, the team is ...
Question 10: A change made to the internal structure of software that mak...
Question 11: An agile practitioner notices that team members are disengag...
Question 12: A company is starting to introduce Agile practices, and the ...
Question 13: The team underestimated the complexity of a story, resulting...
Question 14: Which type of estimate refers to estimating a story based on...
Question 15: During a team meeting, members who are subject matter expert...
Question 16: A seven-member agile team's composition varies considerably ...
Question 17: Based on the following information, determine the number wee...
Question 18: Scrum practices are facilitated by the:...
Question 19: A newly formed scrum team wants to foster an environment of ...
Question 20: During a project meeting, a team is faced with a difficult d...
Question 21: The Kaizen philosophy is change:...
Question 22: The product owner of a team starts the iteration review with...
Question 23: An agile project manager notices that the product owner mana...
Question 24: How should a project leader manage stakeholder expectations ...
Question 25: A project team identifies a number of technical challenges w...
Question 26: Pick the two PMLC models that are based upon the Agile Proje...
Question 27: What is the first thing an agile development team should do ...
Question 28: Which of the following is most appropriate to always partici...
Question 29: While reviewing the sprint burn down during a stand up. the ...
Question 30: Estimating costs for an Agile project starts with which of t...
Question 31: As user stories are developed, what should be done to record...
Question 32: Project managers use velocity to determine:...
Question 33: During a retrospective, team members suggest process improve...
Question 34: A project's first iteration contains item A, and its second ...
Question 35: If the Sprint Backlog cannot be completed in a Sprint, who r...
Question 36: The key elements of a user story in Agile development are:...
Question 37: The purpose of the iteration retrospective is to:...
Question 38: A ScrumMaster:
Question 39: During a retrospective the agile practitioner discovers that...
Question 40: A projects first iteration contains item A and its second it...
Question 41: What can an agile team use to prioritize stories?...
Question 42: A member of the development team is working on a prioritized...
Question 43: An agile team member identifies a potential problem within t...
Question 44: Which of the following is the hierarchy of User Story creati...
Question 45: More details for a story are required before the upcoming sp...
Question 46: An agile practitioner becomes a Scrum Master on an establish...
Question 47: Sprints lengths can vary each Sprint as long as they don't e...
Question 48: A development team for a small company experiences long dela...
Question 49: An organization adopts Agile practices and implements an inc...
Question 50: Business stakeholders of an agile project frequently skip th...
Question 51: A high-performance Agile team:
Question 52: What Scrum event or artifact is the set of items selected fo...
Question 53: A team is creating a highly marketed, time-sensitive product...
Question 54: A development team has finished identifying the tasks they w...
Question 55: Unable to meet a sprint's committed velocity, an agile team ...
Question 56: The purpose of Work in Progress (WIP) limits is to prevent t...
Question 57: The Agile artifact that describes the incremental nature of ...
Question 58: Team A is working on the second sprint of a product release ...
Question 59: What key benefits might stakeholders realize from an Agile a...
Question 60: An agile team has only one database administrator with the n...
Question 61: How is the participatory design process characterized?...
Question 62: An executive sponsor of a new scrum team actively attends sc...
Question 63: What is the ideal approach for an Agile project manager to t...
Question 64: Drag and Drop Question Sequence the core practices of Kanban...
Question 65: An agile project manager notices that the product owner mana...
Question 66: Drag and Drop Question Order the 5 focusing steps of the The...
Question 67: Match each Agile requirement type (on the left) to its defin...
Question 68: On what should Agile estimates be based?...
Question 69: During mid-sprint changes, an agile facilitator meets with t...
Question 70: Who is responsible for determining the business value of eac...
Question 71: What should a Scrum Master do when one team member falls beh...
Question 72: Which of the following is NOT a principle from the Agile Man...
Question 73: During a planning session, four out five team members vote t...
Question 74: A project team identifies a number of technical challenges w...
Question 75: The team estimation game method mainly consists of a:...
Question 76: During mid-sprint changes, an agile facilitator meets with t...
Question 77: Which type of estimation refers to splitting a story into sm...
Question 78: The purpose of "setting the stage'' in a project retrospecti...
Question 79: The cost estimation techniques used on Agile projects are:...
Question 80: Based on the chart, what is the current status of the iterat...
Question 81: A product owner feels that the last sprint failed to suffici...
Question 82: When is the ideal time to hold a retrospective?...
Question 83: Drag and Drop Question The PM Declaration of Interdependence...
Question 84: Which Agile method goes through the following stages: (Exhib...
Question 85: The 80/20 rule is also known as what law?...
Question 86: A scrum team has eight developers, but only two are database...
Question 87: How can an agile practitioner ensure that all key stakeholde...
Question 88: A development team for a small company experiences long dela...
Question 89: What is used to provide a simple medium for gathering basic ...
Question 90: Which of the following is an example of an information radia...
Question 91: Which best describes the attributes of the IN VEST criteria ...
Question 92: A team is transitioning from a predictive approach to an agi...
Question 93: In a vision meeting, the vision for the project is defined a...
Question 94: Which statement is least accurate when providing a definitio...
Question 95: A team member has spent 5 days on a spike and the first set ...
Question 96: During a retrospective the agile practitioner discovers that...
Question 97: Which of the following are 2 attributes of Exploratory testi...
Question 98: The measure of productivity of a Kanban team is:...
Question 99: What is the normal time estimate for a research story?...
Question 100: The advantage of face-to-face collaboration emphasized in eX...
Question 101: While reviewing the sprint burn down during a stand up, the ...
Question 102: A user story says that a product must be very fast. During t...
Question 103: When estimating initial velocity, the team should most likel...
Question 104: The following chart lists stories for a release of an Agile ...
Question 105: A project sponsor is upset that an enhancement will be unava...
Question 106: Drag and Drop Question The Agile Manifesto states we value s...
Question 107: A client states that a product is not being built as request...
Question 108: Which is the first step in setting up Kanban?...
Question 109: During product development, changes in technology and regula...
Question 110: Midway through a two-week sprint, an agile team realizes tha...
Question 111: A technical problem arises that will likely impact the stori...
Question 112: A project manager is concerned that the team has misaligned ...
Question 113: Which of the following is a STORY?...
Question 114: When can a plan be changed in Agile Management?...
Question 115: The ScrumMaster and the Product Owner disagree on the value ...
Question 116: Sequence the steps to User Story Mapping. (Exhibit)...
Question 117: The product owner should spend at least 3 hours per day with...
Question 118: Which of the following is a list of valid Agile project plan...
Question 119: In the Agile Team Stages of Shu Ha Ri, what does 'Ha' stand ...
Question 120: Who can change the Sprint Backlog during a Sprint?...
Question 121: An Agile team expects a velocity of 8. During sprint plannin...
Question 122: This Emertxe Project Management (MPx) approach is when neith...
Question 123: What is the responsibility of an extreme Programming (XP) cu...
Question 124: During a planning session, four out five team members vote t...
Question 125: Collaboration can be defined as working together to jointly ...
Question 126: An Artifact on an Agile project can best be described as:...
Question 127: After completing the release plan, the team realizes that th...
Question 128: What should a learn do when they complete ail sprint goals e...
Question 129: The term "last responsible moment" refers to the moment at w...
Question 130: While struggling to take ownership of delivery, an agile tea...
Question 131: A ScrumMaster:
Question 132: Technical debt is the total amount of less-than perfect ____...
Question 133: Which is NOT a Scrum Role?
Question 134: A product owner asks a newly formed scrum team how many stor...
Question 135: What Agile planning artifact should be updated at minimum se...
Question 136: When are acceptance tests typically written for a user story...
Question 137: All of the following are metrics used in Agile except:...
Question 138: During a six-week iteration, an issue is identified by a tea...
Question 139: When managing an agile software team, engaging the business ...
Question 140: A common estimation unit for Agile projects is:...
Question 141: The Kaizen philosophy is change:...
Question 142: A member of a project's development team approaches the team...
Question 143: What is the best definition of "Done"?...
Question 144: A ScrumMaster consistently holds Daily Scrums and keeps them...
Question 145: A new product owner shares the product vision during the tea...
Question 146: Which are some of the most important benefits of an Agile te...
Question 147: What is the first thing that a team should do to estimate us...
Question 148: During a Kanban team's daily stand up, an agile coach observ...
Question 149: The advantage of face-to-face collaboration emphasized in eX...
Question 150: The Product Owner is the sole person responsible for managin...
Question 151: The Scrum Master as a Servant Leader is in service to which ...
Question 152: After three iterations, the problems impeding an Agile team ...
Question 153: What is the first thing an agile development team should do ...
Question 154: Which term best describes an Agile project's approach to ris...
Question 155: During a backlog refinement meeting, a senior team member ra...
Question 156: Which of the following is NOT considered an enterprise Agile...
Question 157: How does Empirical Process Control support Agile methodologi...
Question 158: Which tool allows the Product Owner to focus on providing th...
Question 159: Continuous integration ensures that a product is:...
Question 160: In an Agile approach, project values are most effectively im...
Question 161: Which of the following is most appropriate to always partici...
Question 162: Order the 5 focusing steps of the Theory of Constraints. (Ex...
Question 163: Which of the following best describes a core belief of Agile...
Question 164: This artifact contains release names with expected dates and...
Question 165: Which layer of the product planning structure defines detail...
Question 166: The purpose of a project burndown chart is to:...
Question 167: The following chart lists stories for a release of an Agile ...
Question 168: What Agile concept expresses delivering value in slices rath...
Question 169: When implementing Agile Project Management, risk management ...
Question 170: There must be a release every Sprint....
Question 171: A scrum team has conducted regular retrospectives to discuss...
Question 172: The Scrum Master is a management role?...
Question 173: When prioritizing features to be delivered in an iteration, ...
Question 174: In the Lean process, the focus is on:...
Question 175: During a current sprint a learn member asks permission horn ...
Question 176: Which of the following best represents both a principle of t...
Question 177: After three iterations, it is identified that a project's un...
Question 178: The purpose of Work in Progress (WIP) limits is to prevent t...
Question 179: Estimating costs for an Agile project starts with which of t...
Question 180: Which type of estimate refers to estimating a story based on...
Question 181: Drag and Drop Question Pick which 3 activities are the respo...
Question 182: A company is considering developing a new, complex applicati...
Question 183: The executive leadership wants to understand ways to better ...