<< Prev Question Next Question >>

Question 190/381

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (381q)
Question 1: Through whom do project managers accomplish work?...
Question 2: Project managers who lead by example and follow through on t...
Question 3: Which process involves documenting the actions necessary to ...
Question 4: What is the difference between the critical path and the cri...
Question 5: A project has an EV of 100 workdays, an AC of 120 workdays, ...
Question 6: Which activity may occur at project or phase closure?...
Question 7: A graphic display of project team members and their reportin...
Question 8: Enterprise environmental factors are an input to which proce...
Question 9: Outputs of the Control Communications process include:...
Question 10: Which statement summarizes the role of the change control bo...
Question 11: The basis of identification for current or potential problem...
Question 12: Which type of organizational structure is displayed in the d...
Question 13: Identify Stakeholders is the process of identifying all of t...
Question 14: Which quality tool incorporates the upper and lower specific...
Question 15: Progressively elaborating high-level information into detail...
Question 16: Monte Carlo is which type of risk analysis technique?...
Question 17: The project team is using their current information, abiliti...
Question 18: What is the critical chain method?...
Question 19: The definition of operations is a/an:...
Question 20: A project management office manages a number of aspects incl...
Question 21: A project had four phases, and at the end of the third phase...
Question 22: A project manager needs to tailor the Project Cost Managemen...
Question 23: Ensuring that both parties meet contractual obligations and ...
Question 24: Which of the following is a tool and technique for Estimate ...
Question 25: Which of the following is a conflict resolution technique th...
Question 26: Which of the following is an input to the Direct and Manage ...
Question 27: The formal and informal interaction with others in an organi...
Question 28: Which of the following is an information gathering technique...
Question 29: Which of the following is a strategy to deal with positive r...
Question 30: Which project manager competency is displayed through the kn...
Question 31: Typical outcomes of a project include:...
Question 32: The features and functions that characterize a result, produ...
Question 33: Which item is an example of personnel assessment?...
Question 34: The item that provides more detailed descriptions of the com...
Question 35: A project manager is estimating project activities using an ...
Question 36: Which of the following is a component of three-point estimat...
Question 37: Which written document helps monitor who is responsible for ...
Question 38: Identify Risks is part of which Process Group?...
Question 39: Retreating from an actual or potential conflict or postponin...
Question 40: Which set of tools and techniques is useful for estimating a...
Question 41: Which of the following are an enterprise environmental facto...
Question 42: Projects, programs, subsidiary portfolios, and operations ma...
Question 43: Which type of dependency is established based on knowledge o...
Question 44: Which document in the project management plan can be updated...
Question 45: Which of the following change requests can bring expected fu...
Question 46: If a project manager effectively manages project knowledge, ...
Question 47: With regard to a project manager's sphere of influence in a ...
Question 48: Projects are authorized by which of the following individual...
Question 49: What communication methods would a project manager use for o...
Question 50: A key benefit of the Manage Communications process is that i...
Question 51: A project manager needs to request outside support for a sta...
Question 52: When should Project Risk Management be conducted?...
Question 53: The project budget is set at $150,000. The project duration ...
Question 54: Which of the following terms indicates a deliverable-oriente...
Question 55: The business needs, assumptions, and constraints and the und...
Question 56: What is the schedule performance index (SPI) if the planned ...
Question 57: Reserve analysis is a tool and technique used in which proce...
Question 58: In agile projects while performing scope management, what is...
Question 59: Change request status updates are an output of which process...
Question 60: Which input to Collect Requirements is used to identify stak...
Question 61: The ways in which the roles and responsibilities, reporting ...
Question 62: In Project Resource Management, which process uses recogniti...
Question 63: Which set of competencies should a project manager have?...
Question 64: Which Process Group and Knowledge Area include the Sequence ...
Question 65: An input required to develop a preliminary project scope sta...
Question 66: The process improvement plan details the steps for analyzing...
Question 67: In a construction project schedule, what is the logical rela...
Question 68: Which of the following is TRUE about most project life cycle...
Question 69: Given the following information: - Activity A takes one week...
Question 70: Activity resource requirements and the resource breakdown st...
Question 71: Which format can a network diagram take?...
Question 72: Labor, materials, equipment, and supplies are examples of:...
Question 73: An intentional activity to modify a nonconforming product or...
1 commentQuestion 74: Which of the following strategic considerations often result...
Question 75: In the Initiating Process Group, at what point does the proj...
Question 76: Which provides the basic framework for managing a project?...
Question 77: A project is in progress and about to move to a different ph...
Question 78: A project manager called for a team meeting to estimate the ...
Question 79: Which tool is used to develop technical details within the p...
Question 80: Which process identifies whether the needs of a project can ...
Question 81: Which is a list of organizational systems that may have an i...
Question 82: An output of Control Schedule is:...
Question 83: The technique of subdividing project deliverables into small...
Question 84: Which of the following is an input to the Plan Risk Response...
Question 85: As part of a mid-project evaluation, the project sponsor has...
Question 86: The project manager is dividing the project scope into small...
Question 87: How is the Project Scope Management process different in agi...
Question 88: The individual or group that provides resources and support ...
Question 89: In which process might a project manager use risk reassessme...
Question 90: Which of the following investigates the likelihood that each...
Question 91: A required input for Create WBS is a project:...
Question 92: The risk management team of a software project has decided t...
Question 93: The initial development of a Project Scope Management plan u...
Question 94: A project manager is determining the amount of contingency n...
Question 95: The iterative process of increasing the level of detail in a...
Question 96: In a preliminary meeting for a project, team members decide ...
Question 97: An output of the Manage Stakeholder Engagement process is:...
Question 98: Which of the following involves making information available...
Question 99: Which Project Management Process Group includes Collect Requ...
Question 100: The probability and impact matrix is primarily used to:...
Question 101: Inputs to the Plan Risk Management process include the:...
Question 102: Which of the following documents are created as part of Proj...
Question 103: Which of the following is a tool and technique used in all p...
Question 104: Which defines the portion of work included in a contract for...
Question 105: Which stakeholder approves a project's result?...
Question 106: A project manager held a meeting and listed all team members...
Question 107: What output of the Conduct Procurements process is also an i...
Question 108: What are the components of the "triple constraint "?...
Question 109: Those who enter into a contractual agreement to provide serv...
Question 110: Which type of dependency used in the Sequence Activities pro...
Question 111: How can a project manager determine if the project activitie...
Question 112: What is a deliverable-oriented, hierarchical decomposition o...
Question 113: Which of the following can a project manager use to represen...
Question 114: What are the four management processes included in the Proje...
Question 115: Which item is an input to the Define Activities process?...
Question 116: Projects can intersect with an organization's operations at ...
Question 117: A project manager of a civil construction project is trying ...
Question 118: The cost performance baseline is typically displayed in the ...
Question 119: Which conflict resolution technique searches for solutions t...
Question 120: In a functional organization, the director of an important s...
Question 121: Types of internal failure costs include:...
Question 122: In which Process Group are lessons learned documented?...
Question 123: To please the customer, a project team member delivers a req...
Question 124: A project report completed an earned value (EV) of US $45 fo...
Question 125: What scope definition technique is used to generate differen...
Question 126: At which point of the project is the uncertainty the highest...
Question 127: In a project using agile methodology, who may perform the qu...
Question 128: Which of the following helps to ensure that each requirement...
Question 129: Which of the following processes are part of the Project Int...
Question 130: Job satisfaction, challenging work, and sufficient financial...
Question 131: Which Process Group typically consumes the bulk of a project...
Question 132: A project manager needs to demonstrate that the project meet...
Question 133: Which is the order of steps in the Procurement Management pr...
Question 134: What type of project structure is a hierarchically organized...
Question 135: Risk responses reflect an organization's perceived balance b...
Question 136: Which activity involves ensuring that the composition of a p...
Question 137: Which of the following is an output from Control Scope?...
Question 138: What is the name of a graphic display of project team member...
Question 139: Another name for an Ishikawa diagram is:...
Question 140: Requirements documentation, requirements management plan, an...
Question 141: An output of the Perform Integrated Change Control process i...
Question 142: A method to manage stakeholder expectations in the scope sta...
Question 143: Which of the following is an output of the Conduct Procureme...
Question 144: The Agile principle "welcome changing requirements, even lat...
Question 145: Which of the following is an example of the objective of a q...
Question 146: A new project manager wishes to recommend creating a project...
Question 147: What is the purpose of tailoring in project management?...
Question 148: The planned work contained in the lowest level of work break...
Question 149: A full-time project manager with low to moderate authority a...
Question 150: Quality metrics are an output of which process?...
Question 151: One of the key benefits of the Plan Human Resource Managemen...
Question 152: Which of the following correctly describes when organization...
Question 153: Which of the following is an example of a technique used in ...
Question 154: Within project integration management, the statement of work...
Question 155: The project manager and the project team are having a meetin...
Question 156: A Pareto chart is a specific type of:...
Question 157: Which process uses occurrence probability and impact on proj...
Question 158: Which task will a project manager undertake while conducting...
Question 159: What are the identified risks for doing excessive decomposit...
Question 160: Analytical techniques are a tool and technique of which proc...
Question 161: Which process involves defining, preparing, and coordinating...
Question 162: In which project cost management process is work performance...
Question 163: The CPI is .92, and the EV is US$172,500.What is the actual ...
Question 164: Which of the following is a tool or technique used in the De...
Question 165: Which of the following schedule network analysis techniques ...
Question 166: Success is measured by benefits realization for a:...
Question 167: Soft logic is also known as what type of dependency?...
Question 168: Change requests are processed for review and disposition acc...
Question 169: Which of the following is an output of the Perform Integrate...
Question 170: According to the PMI Talent Triangle, leadership skills rela...
Question 171: Which of the following outputs from the Control Schedule pro...
Question 172: A project manager is formalizing acceptance of the completed...
Question 173: A risk that arises as a direct result of implementing a risk...
Question 174: What happens to a stakeholder's project influence over time?...
Question 175: The following is a network diagram for a project. (Exhibit) ...
Question 176: Resource calendars are included in the:...
Question 177: Which of the following is a category of organizational proce...
Question 178: Who is responsible for determining which processes from the ...
Question 179: Which is a tool or technique used in Define Scope?...
Question 180: Which estimating technique uses the actual costs of previous...
Question 181: The PV is $1000, EV is $2000, and AC is $1500. What is CPI?...
Question 182: A benefit of using virtual teams in the Acquire Project Team...
Question 183: Which of the following buffers protects the target finish da...
Question 184: Which of the following is an input to the Perform Qualitativ...
Question 185: The project manager has the following information about the ...
Question 186: A measure of cost performance that is required to be achieve...
Question 187: Which factors should be considered for cross-cultural commun...
Question 188: A new project has been set. Four main stakeholders besides t...
Question 189: Which of the following statements is true regarding project ...
Question 190: Which is an example of leveraging evolving trends and emergi...
Question 191: Which type of analysis is used as a general management techn...
Question 192: Which process is responsible for monitoring the status of th...
Question 193: A company must implement sales software because it is openin...
Question 194: A project has an estimated duration of 10 months with a tota...
Question 195: Under which circumstances should multiple projects be groupe...
Question 196: The project scope statement and resource calendars are input...
Question 197: Which activity is an input to the Conduct Procurements proce...
Question 198: The project manager is using co-location and providing train...
Question 199: The zero duration of milestones in project planning occurs b...
Question 200: To which process is work performance information an input?...
Question 201: A project manager requesting industry groups and consultants...
Question 202: Which of the following is the correct network diagram for th...
Question 203: The following is a network diagram for a project. (Exhibit) ...
Question 204: What does an S-curve from a Monte Carlo analysis show?...
Question 205: What causes replanning of the project scope?...
Question 206: What organizational asset can influence the Plan Risk Manage...
Question 207: Stakeholders can be identified in later stages of the projec...
Question 208: An input to the Control Quality process is:...
Question 209: Which input provides suppliers with a clear set of goals, re...
Question 210: An imposed date for completion of the project by the custome...
Question 211: Which standard examines an enterprise's project management p...
Question 212: Which enterprise environmental factors are considered during...
Question 213: Projects are separated into phases or subprojects; these pha...
Question 214: What type of reward can hurt team cohesiveness?...
Question 215: At the start of a typical project life cycle, costs are:...
Question 216: Which Define Activities tool or technique is used for dividi...
Question 217: What is the primary benefit of meeting quality requirements?...
Question 218: The Monitoring and Controlling Process Group includes proces...
Question 219: Project Scope Management is primarily concerned with:...
Question 220: Creating the project scope statement is part of which proces...
Question 221: Tools and techniques used in Direct and Manage Project Work ...
Question 222: Which type of dependency is legally or contractually require...
Question 223: Which of the following correctly explains the term "progress...
Question 224: Which of the following is an output of Define Scope?...
Question 225: A project manager is in the process of working with stakehol...
Question 226: The process for performing variance analysis may vary, depen...
Question 227: The chart below is an example of a: (Exhibit)...
Question 228: An input to Close Project or Phase is:...
Question 229: Which of the following is a tool or technique used in the Ac...
Question 230: Which of the following is an input to Control Scope?...
Question 231: The component of the risk management plan that documents how...
Question 232: Which tool or technique allows a large number of ideas to be...
Question 233: In which process is a project manager identified and given t...
Question 234: The primary purpose of the stakeholder register is to:...
Question 235: Which of the following methods of performance review examine...
Question 236: What is the order of the stages of project team development?...
Question 237: Which of the following statements best describes the influen...
Question 238: When is a project finished?
Question 239: Assigned risk ratings are based upon:...
Question 240: What is the number of stakeholders, if the project has 28 po...
Question 241: Which statement about accepted deliverables is correct?...
Question 242: A weighting system is a tool for which area of Conduct Procu...
Question 243: A project manager has created an issue log to document issue...
Question 244: The process of prioritizing risks for further analysis or ac...
Question 245: A functional manager is delegating a key project to a projec...
Question 246: What is a hierarchically organized depiction of the identifi...
Question 247: When painting a bedroom, preparing the walls can be done whi...
Question 248: An important project stakeholder has low risk tolerance. Whi...
Question 249: Which Control Scope input is compared to actual results to d...
Question 250: Which of the following is a schedule network analysis techni...
Question 251: Which piece of information is part of the WBS Dictionary?...
Question 252: The run chart created during the Perform Quality Control pro...
Question 253: Which is a communication method used in the Report Performan...
Question 254: The cost of nonconformance in a project includes:...
Question 255: Which tool or technique of the Define Activities process all...
Question 256: Which of the following is a means of reaching a group decisi...
Question 257: Which of the following strategies is used to deal with risks...
Question 258: Which statement correctly describes the value of a business ...
Question 259: Which type of project life cycle uses an iteration plan?...
Question 260: Cost of quality (COQ) refers to total cost of/to:...
Question 261: A project's purpose or justification, measurable project obj...
Question 262: Which type of chart is a graphic representation of a process...
Question 263: Which schedule development technique modifies the project sc...
Question 264: To which knowledge area does the Collect Requirements proces...
Question 265: Which knowledge area includes the processes to identify, def...
Question 266: The document that guides project execution, monitoring and c...
Question 267: Which Knowledge Area is concerned with the processes require...
Question 268: Which of the following is an output of the Plan Quality proc...
Question 269: A project manager should communicate to stakeholders about r...
Question 270: A tool and technique used during the Perform Qualitative Ris...
Question 271: A temporary endeavor that creates a unique product or servic...
Question 272: Which components of the project can be updated as a result o...
Question 273: What tool and technique is used to determine whether work an...
Question 274: PMBOI Guide is a standard that describes:...
Question 275: In the Develop Project Team process, which of the following ...
Question 276: Which of the following is a tool and technique used in the D...
Question 277: The degree, amount, or volume of risk that an organization o...
Question 278: The Verify Scope process is primarily concerned with:...
Question 279: The purpose of the Project Communications Management Knowled...
Question 280: Which tool or technique is used in the Plan Scope Management...
Question 281: Which can be used to determine whether a process is stable o...
Question 282: During which process group is the quality policy determined?...
Question 283: Which process determines the risks that might affect the pro...
Question 284: What are the key components of the communication model?...
Question 285: Which of the following sets are inputs to the Collect Requir...
Question 286: Using parametric estimating, if an assigned resource is capa...
Question 287: In order to detect quality issues earlier in the project lif...
Question 288: Prioritizing risks for further analysis or action by assessi...
Question 289: Which type of contract is most commonly used by buying organ...
Question 290: Lessons learned are created and project resources are releas...
Question 291: A project manager who communicates to the project team thoug...
Question 292: Which group creativity technique asks a selected group of ex...
Question 293: Which are required to create the schedule management plan?...
Question 294: The risk response strategy in which the project team acts to...
Question 295: The project governance approach should be described in the:...
Question 296: The project charter is an input to which process?...
Question 297: Variance and trend analysis is a tool and technique used in ...
Question 298: Which of the following lists represents the outputs of the M...
Question 299: Lessons learned documentation is gathered during which of th...
Question 300: Which illustrates the connection between work that needs to ...
Question 301: Grouping the stakeholders based on their level of authority ...
Question 302: The procurement requirements for a project include working w...
Question 303: A tool and technique used during the Define Scope process is...
Question 304: The project manager is working in an agile/adaptive environm...
Question 305: Which input to the Identify Stakeholders process provides in...
Question 306: Which tool or technique is used to develop the human resourc...
Question 307: Which process involves aggregating the estimated costs of th...
Question 308: Sending letters, memos, reports, emails, and faxes to share ...
Question 309: Which is an enterprise environmental factor?...
Question 310: An input used in developing the communications management pl...
Question 311: Which project documents can determine the budget?...
Question 312: An example of a group decision-making technique is:...
Question 313: Which of the Project Time Management processes analyzes acti...
Question 314: Which stakeholder communicates with higher levels of managem...
Question 315: Which of these is true of a project schedule?...
Question 316: A project manager is working on an estimate. The project tea...
Question 317: Due to today's competitive global market, organizations requ...
Question 318: Which project risk listed in the table below is most likely ...
Question 319: What are the inputs of the Estimate Costs process?...
Question 320: A project manager is monitoring and recording results of exe...
Question 321: The following chart contains information about the tasks in ...
Question 322: In which sphere of influence is the project manager demonstr...
Question 323: Managing procurement relationships and monitoring contract p...
Question 324: Which process is included in the Project Integration Managem...
Question 325: Which of the following set of elements is part of an effecti...
Question 326: Which process involves subdividing project deliverables and ...
Question 327: The ability to influence cost is greatest during which stage...
Question 328: Organizational process assets can be divided into which of t...
Question 329: Which is an output of the Collect Requirements process?...
Question 330: The Perform Quality Assurance process occurs in which Proces...
Question 331: Which technique is utilized in the Control Schedule process?...
Question 332: Which of the following characteristics are found in a functi...
Question 333: Information collected on the status of project activities be...
Question 334: Managing ongoing production of goods and services to ensure ...
Question 335: In the Estimate Activity Durations process, productivity met...
Question 336: Which tool and technique is used in Conduct Procurements?...
Question 337: A project charter is an output of which Process Group?...
Question 338: Which item is a formal proposal to modify any document, deli...
Question 339: Which is a tool used in monitoring and controlling project w...
Question 340: Which are the competing constraints that a project manager s...
Question 341: The project manager implemented the stakeholder engagement p...
Question 342: An effective technique for resolving conflict that incorpora...
Question 343: Configuration identification, configuration status accountin...
Question 344: If you are using an Ishikawa diagram to determine the root c...
Question 345: A firm contracted an event management company to conduct the...
Question 346: Which characteristic do projects and operational work share ...
Question 347: Control charts, flowcharting, histograms, Pareto charts, and...
Question 348: When project requirements are documented in user stories the...
Question 349: A project conducts regular standup meetings to keep everyone...
Question 350: The project management processes presented in the PMBOK Guid...
Question 351: Which process documents the business needs of a project and ...
Question 352: The Process Group that involves coordinating people and reso...
Question 353: What is the function of a Project Management Office (PMO)?...
Question 354: The focus on continuous communication with all stakeholders,...
Question 355: In a typical project, project managers spend most of their t...
Question 356: Which process develops options and actions to enhance opport...
Question 357: Which of the following is an input to the Develop Project Ch...
Question 358: The diagram below is an example of a: (Exhibit)...
Question 359: In which type of contract are the performance targets establ...
Question 360: The component of the human resource management plan that inc...
Question 361: Which is an input to the Scope Verification Process?...
Question 362: What is both an input and output of the Control Quality proc...
Question 363: The lowest level normally depicted in a work breakdown struc...
Question 364: Documented identification of a flaw in a project component t...
Question 365: Which earned value management (EVM) metric is a measure of t...
Question 366: Which tool or technique is used to manage change requests an...
Question 367: Which of the following is an output of the Distribute Inform...
Question 368: Which characteristic is unique to project work and does not ...
Question 369: Co-location is a tool and technique of:...
Question 370: The project manager needs to review the templates in use. Th...
Question 371: Taking out insurance in relation to risk management is calle...
Question 372: Which process in Project Time Management includes reserve an...
Question 373: Which schedule network analysis technique modifies the proje...
Question 374: Which is the tool or technique that is used to obtain the li...
Question 375: The three processes of Project Cost Management are:...
Question 376: If the most likely duration of an activity is five weeks, th...
Question 377: When addressing roles and responsibilities, which item ensur...
Question 378: Which process should be conducted from the project inception...
Question 379: The risk shared between the buyer and seller is determined b...
Question 380: Which group of inputs will a project manager use during the ...
Question 381: Perform Quality Control is accomplished by:...