Valid ISO-9001-Lead-Auditor Dumps shared by ExamDiscuss.com for Helping Passing ISO-9001-Lead-Auditor Exam! ExamDiscuss.com now offer the newest ISO-9001-Lead-Auditor exam dumps, the ExamDiscuss.com ISO-9001-Lead-Auditor exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com ISO-9001-Lead-Auditor dumps with Test Engine here:
The following actions need to be carried out during a third-party audit planning stage. Which two actions correspond to the individual(s) managing the audit program before the involvement of the audit team leader'
Correct Answer: D,E
In ISO 9001:2015, the responsibility for managing the audit program lies with those overseeing the entire audit process rather than the Audit Team Leader. During the planning stage, before involving the Audit Team Leader, key actions for managing the audit program include: 1. Providing the Resources Needed: According to clause 7.1 (Resources), the audit program manager must ensure that the necessary resources are in place to conduct the audit effectively. This encompasses logistical support, personnel, and other required resources for the audit to proceed smoothly. 2. Reviewing Reports of Previous Audits: As per clause 9.2.2 (Internal Audit), it is essential to consider the results of previous audits to plan effectively for the upcoming audit. This helps identify areas that require particular attention, ensuring continuity and focusing on recurring issues or improvements since the last audit. These actions ensure that the audit is thoroughly prepared and that there is continuity and focus on any areas that might need closer inspection. The other options, such as preparing the audit plan, assigning responsibilities, preparing checklists, and selecting the audit team members, generally fall under the duties of the Audit Team Leader once they are appointed and engaged in the planning process.