Valid 1Z0-511 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-511 Exam! ExamDiscuss.com now offer the newest 1Z0-511 exam dumps, the ExamDiscuss.com 1Z0-511 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-511 dumps with Test Engine here:
A company generates revenue at period end, but bills monthly in advance. The customer is invoiced in April with project starting in May and the first project is due to be recognized at the end of May. What are the accounting entries at the end of May?
Correct Answer: D
Explanation/Reference: Explanation: Invoice When you run the program to interface invoices to Oracle Receivables, Oracle Projects runs AutoAccounting to determine the appropriate default accounts. If the invoice fails AutoAccounting, then the program marks the draft invoice with an error. See: Overview of AutoAccounting, Oracle Projects Implementation Guide. The following table shows entries Oracle Projects creates when the Interface Invoices to Oracle Receivables process is run: AccountDebitCredit Receivables200.00 Unbilled Receivables and/or Unearned Revenue200.00 References: