Valid 1Z0-1075 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-1075 Exam! ExamDiscuss.com now offer the newest 1Z0-1075 exam dumps, the ExamDiscuss.com 1Z0-1075 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-1075 dumps with Test Engine here:
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours. The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon. What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?