A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is
assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given
work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (23q)
Question 1: During a Manufacturing Cloud implementation, the customer re...
Question 2: You want to use a predefined Standard Operation in a Work De...
Question 3: Identify three entities that must be set up in Oracle Manufa...
Question 4: You have been asked to set up cost estimates for 10 differen...
Question 5: Identify two conditions that should be met at the same time ...
Question 6: You can generate and manage work order exceptions in Oracle ...
Question 7: One of the key execution capabilities that Oracle Manufactur...
Question 8: A plant operates three continuous daily shifts of eight hour...
Question 9: Which entity should you use to configure the manufacturing p...
Question 10: A production operator needs to review the materials issued, ...
Question 11: A plant runs 24x7 daily using three continuous shifts of 8 h...
Question 12: Your customer plans to use Oracle Representational State Tra...
Question 13: A Work Center created a month ago is no longer in use now. Y...
Question 14: An order entry specialist creates a Back-to-Back order for p...
Question 15: Which two steps should you use to create a new Oracle Transa...
Question 16: In what three ways can you set the overcompletion tolerance ...
Question 17: A Manufacturing Engineer in a plant is creating an alternati...
Question 18: In a manufacturing plant, a production operator in a given s...
Question 19: The Cost Accountant has reported to the Production Superviso...
Question 20: Identify two reports that provide work order cost-related in...
Question 21: In a Manufacturing Cloud post production support environment...
Question 22: The production user wants to report Work Order completion. I...
Question 23: During a Manufacturing Cloud implementation, the Production ...