Valid 1z0-1057-20 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-1057-20 Exam! ExamDiscuss.com now offer the newest 1z0-1057-20 exam dumps, the ExamDiscuss.com 1z0-1057-20 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-1057-20 dumps with Test Engine here:
You create a project schedule with a Shifts element. Identify two more elements that can be part of a project schedule. (Choose two.)
Correct Answer: A,C
Explanation Reference https://docs.oracle.com/cloud/latest/projectcs_gs/FAPFM/FAPFM1192914.htm Topic - Creating Calendars for Projects and Resources: Procedure Project Schedules are used as a base for project and resource calendars in Project Execution Management applications. The smallest scheduling unit is a day. For example, you can define the number of hours in a day but, you can't schedule work for a specific time of the day. The following are the elements of a schedule: * Shifts * Workday patterns * Exceptions