Valid 1Z0-1008 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-1008 Exam! ExamDiscuss.com now offer the newest 1Z0-1008 exam dumps, the ExamDiscuss.com 1Z0-1008 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-1008 dumps with Test Engine here:
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments.