You are working on a remote Exadata Database Machine with current software and firmware. You now need to start a storage server after hardware maintenance. Which ILOM command starts the storage server?
Correct Answer: F
ILOM (Integrated Lights Out Manager) is a remote management system that allows you to control and monitor Exadata Database Machine components, such as storage servers and database servers, from a remote location. The command "start /SYS/power" is used to power on the storage server in the Exadata Database Machine after hardware maintenance. This command can be executed remotely via ILOM.