Which set of steps is the recommended cabling sequence with FS1-2 hardware components?
A. 1. Controller 1: Install CMA, plug and route cables Power first, Ethernet, SASController Interconnects, SAS Controller to Strings and Front End Network Connections respectively. 2. Controller 2: Same as above. 3. DEs per string sequence. 4. Pilot 1: Install CMA, plug al cables and route them Power first, Ethernet Last. 5. Pilot 2: Same as above.
B. 1. Pilot 1: Install CMA, plug all cables, and route them Power first, Ethernet Last. 2. Pilot 2: Same as above. 3. Controller 1: Install CMA, plug and route cables Power first, Ethernet, SAS Controller Interconnects, SAS Controller to Strings and Front End Network Connections respectively. 4. Controller 2: Same as above. 5. DEs per string sequence.
C. 1. Controller 1: Install CMA, plug and route cables Power first, Ethernet, SAS Controller Interconnects, SAS Controller to Strings, and Front End Network Connections respectively. 2. Controller 2: Same as above. 3. Pilot 1: Install CMA, plug all cables, and route them Power first, Ethernet last. 4. Pilot 2: Same as above. 5. DEs per string sequence.
D. 1. Pilot 1: Install CMA, plug all cables, and route them Power first, Ethernet last. 2. Pilot 2: Same as above. 3. DEs per string sequence. 4. Controller 1: Install CMA, plug and route cables Power first, Ethernet, SAS Controller Interconnects, SAS Controller to Strings, and Front End Network Connections respectively. 5. Controller 2: Same as above.