Valid 1Z0-1057-23 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-1057-23 Exam! ExamDiscuss.com now offer the newest 1Z0-1057-23 exam dumps, the ExamDiscuss.com 1Z0-1057-23 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-1057-23 dumps with Test Engine here:
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure. Identify the correct statement about the RBS and new resources. (Choose the best answer.)
Correct Answer: B
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/fapfm/implementing-project-financial-management-applications.html#FAPFM969761 Topic - Entering Planning Resource Breakdown Structure Details Click Navigator > Setup and Maintenance, and search for the Manage Planning and Billing Resource Breakdown Structures task. Click the Manage Planning and Billing Resource Breakdown Structures link. Use the Manage Planning and Billing Resource Breakdown Structures page to create new planning resource breakdown structures and to review existing planning and billing resource breakdown structures. Click the Create icon in the Planning Resource Breakdown Structures section. Use the Create Planning Resource Breakdown Structure: Basic Information page to provide basic resource breakdown structure information including the name, active dates, and project unit. Enter a planning resource breakdown structure name and select a date from which the resource breakdown structure is available for use. Optionally, provide a description and a date to which the planning resource breakdown structure is available for use. Select a project unit. Only projects created for the selected project unit can use this planning resource breakdown structure. If you want to allow project managers to add planning resources at the project level, then select the Allow resource changes at project level check box. Tip: Changes at the project level don,t move back to the parent planning resource breakdown structure. Deselect this option to ensure all project using the planning resource breakdown structure use the same resources. Optionally, select a Job Set as a source of jobs for creating planning resources on your planning resource breakdown structure. Click Save.