Valid 1D0-1065-23-D Dumps shared by ExamDiscuss.com for Helping Passing 1D0-1065-23-D Exam! ExamDiscuss.com now offer the newest 1D0-1065-23-D exam dumps, the ExamDiscuss.com 1D0-1065-23-D exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1D0-1065-23-D dumps with Test Engine here:
When does the closure phase of the application implementation lifecycle occur?
Correct Answer: C
The closure phase of the application implementation lifecycle occurs at the end of the project. It includes activities such as completing the implementation, transitioning the application to the support team, conducting user training, documenting the project, and conducting a project review or post-implementation evaluation. This phase signifies the end of the implementation process and the transition to ongoing support and maintenance of the application.