Question 3/33

You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
Your FIRST preferred course of action is to:

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (33q)
Question 1: The HATE adhesion tester uses
Question 2: When performing an adhesion test in accordance with ASTM D 3...
Question 3: You are a NACE Level 2 Coating Inspector who has just arrive...
Question 4: Antifouling coatings are regulated by international treaties...
Question 5: Dehumidification is defined as the removal of moisture vapor...
Question 6: Measuring methyl ethyl ketone (MEK) resistance of ethyl sili...
Question 7: Differences in technique for abrasive blasting concrete vers...
Question 8: When a coating is expected to be exposed to temperatures abo...
Question 9: When performing a hardness test on a coating which has elast...
Question 10: When measuring the Dry Film Thickness Of liquid coatings app...
Question 11: The best choice of instrument for holiday testing of thick f...
Question 12: NACE/SSPC Water Jetting standards are directly equivalent to...
Question 13: Non-Conformance Reports are designed to:...
Question 14: Which product, when closely inspected has a green or red lay...
Question 15: Galvanizing performs best in which of the following exposure...
Question 16: NACE Level 2 Inspectors have been authorized to perform:...
Question 17: When observing fabrication defects the NACE Inspector should...
Question 18: Which is used to calibrate a pH meter?...
Question 19: As a NACE Level 2 Inspector, NACE clearly indicates that you...
Question 20: The number of air turns in an enclosure can be affected by a...
Question 21: Which standards are generally established by private-sector ...
Question 22: The Inspectors' goal at the Pre-Job Conference is to:...
Question 23: The most likely area of failure on a buried external pipelin...
Question 24: You are the NACE Inspector on a project where a stationary f...
Question 25: Corrosion is the reverse process of...
Question 26: When conducting inspections the Inspector should follow whic...
Question 27: Because a NACE Level 2 Inspector has been trained in specifi...
Question 28: External coatings applied to buried pipelines are generally ...
Question 29: In powder coatings, when the particles of powder begin to fl...
Question 30: You are the NACE Coating Inspector on a tank lining project ...
Question 31: All of these are advantages of using repair patches EXCEPT...
Question 32: Coating application to concrete substrates is:...
Question 33: Individuals conducting Coating Surveys should:...