Valid PL-900 Dumps shared by ExamDiscuss.com for Helping Passing PL-900 Exam! ExamDiscuss.com now offer the newest PL-900 exam dumps, the ExamDiscuss.com PL-900 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PL-900 dumps with Test Engine here:
You have Power Automate Flow to create a flow that automatically sends email to a project manager when project team members mark a task as complete. Project team members are prematurely marking tasks as complete. You must add quality control into the process by sending an email to a project lead for confirmation that the task is in fact complete before sending the email to the project manager. You need to modify the flow. Which component should you use?
Correct Answer: B
Use a condition and set the action to send an email. Reference: https://docs.microsoft.com/en-us/power-automate/add-condition