You have Power Automate Flow to create a flow that automatically sends email to a project manager when project team members mark a task as complete. Project team members are prematurely marking tasks as complete. You must add quality control into the process by sending an email to a project lead for confirmation that the task is in fact complete before sending the email to the project manager. You need to modify the flow. Which component should you use?
Correct Answer: B
Explanation Use a condition and set the action to send an email. Reference: https://docs.microsoft.com/en-us/power-automate/add-condition