Valid ISTQB-CTFL Dumps shared by ExamDiscuss.com for Helping Passing ISTQB-CTFL Exam! ExamDiscuss.com now offer the newest ISTQB-CTFL exam dumps, the ExamDiscuss.com ISTQB-CTFL exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com ISTQB-CTFL dumps with Test Engine here:
A test manager defined the following test levels in her test plan; Component, System and Acceptance. Which Software Development lifecycle is the Test Manager most likely following?
Correct Answer: A
The test manager is most likely following the V-model for software development. The V-model is a software development model that defines four testing levels that correspond to four development phases: component testing corresponds to component design, integration testing corresponds to architectural design, system testing corresponds to system requirements specification, and acceptance testing corresponds to user requirements specification. The V-model also defines the test planning and test execution activities for each testing level. Agile is a software development model that follows an iterative and incremental approach, where testing is integrated into each iteration and adapts to changing requirements and feedback. Waterfall is a software development model that follows a sequential and linear approach, where testing is performed after the development phase is completed. Prototyping is a softwaredevelopment model that involves creating a simplified version of the software to elicit user feedback and validate requirements before developing the final product. Verified References: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 18.