Valid CTFL-AT Dumps shared by ExamDiscuss.com for Helping Passing CTFL-AT Exam! ExamDiscuss.com now offer the newest CTFL-AT exam dumps, the ExamDiscuss.com CTFL-AT exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTFL-AT dumps with Test Engine here:
A calculator application is being developed. The third sprint has been planned to add functionality to the calculator to allow scientific calculations. Which TWO examples below represent activities that would likely be managed on an agile task board for the third sprint? 1) A task to design the features planned for the next sprint. 2) A task to run an acceptance test for a user story. 3) A task to automate regression tests. 4) A task to participate in training in preparation for the fourth sprint. 5) A task to produce a daily progress report for the agile team members.