Valid CTAL-TM_Syll2012 Dumps shared by ExamDiscuss.com for Helping Passing CTAL-TM_Syll2012 Exam! ExamDiscuss.com now offer the newest CTAL-TM_Syll2012 exam dumps, the ExamDiscuss.com CTAL-TM_Syll2012 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTAL-TM_Syll2012 dumps with Test Engine here:
You have done a comprehensive risk analysis. You have involved the appropriate people in assessing the risks and determining the likelihood and impact of those risks. You have been testing for three months and have been able to mitigate 75% of the high risk items. You have two weeks left in testing and you now do not expect to be able to complete all the items on the high-risk mitigation list, never mind any from the medium or low-risk lists. What is the most effective action you should take? [3]
Correct Answer: B
When faced with the inability to complete all items on the high-risk mitigation list within the remaining time, the most effective action is to communicate the current progress and challenges to the stakeholders. This allows for a collaborative decision-making process to re-prioritize the remaining high-risk items and potentially secure additional resources or time to address them. References:The ISTQB Advanced Level Test Manager syllabus emphasizes the importance of continuous monitoring and control of test activities to achieve project objectives, which includes assessing and reporting relevant and timely test status to project stakeholders123. It also highlights the need for test managers to organize and lead risk identification and analysis sessions, and use the results for test planning, monitoring, and control2.