You are the Test Manager for a critical system and are using a risk-based approach for this project. Which of the following would most clearly convey the current status to project stakeholders? [3]
Correct Answer: C
The most clear way to convey the current status to project stakeholders is to use a pie chart showing residual risk. This is because a risk-based approach focuses on identifying, analyzing, and prioritizing the risks that may affect the quality of the system, and allocating testing resources accordingly. A pie chart can visually represent the proportion of each risk category (such as high, medium, or low) in the overall risk profile, and show how much risk has been reduced or remains after testing. This can help the stakeholders to understand the current level of confidence in the system, and the potential impact of any remaining risks. References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Managing the Test Team - ISTQB not-for-profit association