You are the Test Manager for a new product that is being developed according to an iterative lifecycle. At this point, you have 100% of your smoke tests automated, 20% of your functional tests and 50% of your regression tests. Your iterations are four weeks long. You are finding that with each iteration significant maintenance is required for your automated tests and you are not able to complete the testing within the planned timeframe. The test plan you created at the beginning of the project indicates that all automated tests should be run before any manual tests. Which of the following is a reasonable change to this plan based on how the project is going? [2]
Correct Answer: C
The most reasonable change to the plan based on how the project is going is to continue to run the automated smoke tests first, execute the automated regression test and new manual functional tests in parallel, and discontinue automating any new functional test cases. This is because this option can help to reduce the maintenance effort and time for the automated tests, while still ensuring that the most critical and frequently changed areas are tested adequately. By running the automated smoke tests first, the test team can verify the basic functionality and stability of the new build before proceeding to more detailed testing. By executing the automated regression test and new manual functional tests in parallel, the test team can optimize the use of the available testing resources and cover the most relevant test cases for the current iteration. By discontinuing automating any new functional test cases, the test team can avoid adding more complexity and maintenance overhead to the existing automation suite. Test Automation - ISTQB not-for-profit association References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Test Automation - ISTQB not-for-profit association