For which areas of the enterprise are business continuity plans required?
Correct Answer: A
Explanation/Reference: Explanation: A Business Impact Analysis (BIA) is performed at the beginning of business continuity planning to identify all the areas of the enterprise that would suffer the greatest financial or operational loss in the event of a disaster or disruption. Incorrect Answers: B: All areas of the operations must be considered, not only the financial an information processing areas. C: All areas of the operations must be considered, not only the operating areas. D: All areas of the operations must be considered, not only the marketing, finance, and information processing areas. References: Harris, Shon, All In One CISSP Exam Guide, 6th Edition, McGraw-Hill, 2013, p. 911