Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:

Access CRISC Dumps Premium Version
(1745 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 131/236

The PRIMARY reason to have risk owners assigned to entries in the risk register is to ensure:

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (236q)
1 commentQuestion 1: A risk practitioner has been asked to advise management on d...
Question 2: Which of the following is the MOST effective key performance...
Question 3: An organization striving to be on the leading edge in regard...
Question 4: Which of the following is MOST helpful to management when de...
Question 5: Which of the following provides The MOST useful information ...
Question 6: From a risk management perspective, the PRIMARY objective of...
Question 7: Which of the following is the BEST key performance indicator...
Question 8: It is MOST appropriate for changes to be promoted to product...
Question 9: Which of the following is the MOST important reason to creat...
Question 10: A change management process has recently been updated with n...
Question 11: Which of the following provides the MOST important informati...
Question 12: When determining which control deficiencies are most signifi...
Question 13: The risk associated with an asset before controls are applie...
Question 14: The PRIMARY reason for periodic penetration testing of Inter...
Question 15: Which of the following BEST contributes to the implementatio...
Question 16: The risk appetite for an organization could be derived from ...
Question 17: Which of the following would be the BEST recommendation if t...
Question 18: The MAIN goal of the risk analysis process is to determine t...
Question 19: Which of the following is a detective control?...
Question 20: The analysis of which of the following will BEST help valida...
Question 21: A risk practitioner has identified that the organization's s...
Question 22: A key risk indicator (KRI) indicates a reduction in the perc...
Question 23: Which of the following is the BEST key performance indicator...
Question 24: Establishing and organizational code of conduct is an exampl...
Question 25: Which of the following is the GREATEST concern when using a ...
Question 26: Which of the following is MOST important to understand when ...
Question 27: Implementing which of the following controls would BEST redu...
Question 28: When collecting information to identify IT-related risk, a r...
Question 29: Which of the following is the BEST way for a risk practition...
Question 30: Which of the following would be MOST helpful to an informati...
Question 31: Which of the following is the MOST cost-effective way to tes...
Question 32: Which of the following roles would be MOST helpful in provid...
Question 33: Which of the following IT controls is MOST useful in mitigat...
Question 34: Which of the following is the GREATEST risk associated with ...
Question 35: Which of the following MOST effectively limits the impact of...
Question 36: The head of a business operations department asks to review ...
Question 37: During testing, a risk practitioner finds the IT department'...
Question 38: Which of the following is the PRIMARY responsibility of the ...
Question 39: Which of the following is a crucial component of a key risk ...
Question 40: An application owner has specified the acceptable downtime i...
Question 41: Which of the following will MOST improve stakeholders' under...
Question 42: A risk practitioner observes that the fraud detection contro...
Question 43: Which of the following should be included in a risk assessme...
Question 44: An organization learns of a new ransomware attack affecting ...
Question 45: Which of the following is the MOST appropriate key risk indi...
Question 46: Senior management has asked a risk practitioner to develop t...
Question 47: Which of the following is the PRIMARY purpose of periodicall...
Question 48: Which of the following tools is MOST effective in identifyin...
Question 49: A web-based service provider with a low risk appetite for sy...
Question 50: Which of the following observations would be GREATEST concer...
Question 51: An organization has opened a subsidiary in a foreign country...
Question 52: When reviewing a risk response strategy, senior management's...
Question 53: An organization is unable to implement a multi-factor authen...
Question 54: Which stakeholders are PRIMARILY responsible for determining...
Question 55: A control owner responsible for the access management proces...
Question 56: Which of the following indicates an organization follows IT ...
Question 57: Which of the following is the BEST approach for performing a...
Question 58: Which of the following is the PRIMARY reason to have the ris...
Question 59: Who is the MOST appropriate owner for newly identified IT ri...
Question 60: While evaluating control costs, management discovers that th...
Question 61: Which of the following is the BEST evidence that risk manage...
Question 62: Which of the following is the MOST important component of ef...
Question 63: Which of the following will BEST help an organization evalua...
Question 64: A risk practitioner observes that hardware failure incidents...
Question 65: Which of the following BEST measures the impact of business ...
Question 66: Implementing which of the following will BEST help ensure th...
Question 67: Which of the following requirements is MOST important to inc...
Question 68: Which type of cloud computing deployment provides the consum...
Question 69: A new policy has been published to forbid copying of data on...
Question 70: An organization's risk practitioner learns a new third-party...
Question 71: Which of the following is MOST important to the integrity of...
Question 72: Which of the following is the BEST indication of a mature or...
Question 73: Which of the following is the GREATEST benefit of analyzing ...
Question 74: A recent internal risk review reveals the majority of core I...
Question 75: Which of the following techniques would be used during a ris...
Question 76: Which of the following is the BEST indicator of the effectiv...
Question 77: A bank is experiencing an increasing incidence of customer i...
Question 78: A risk practitioner is reviewing a vendor contract and finds...
Question 79: A peer review of a risk assessment finds that a relevant thr...
Question 80: The MOST effective approach to prioritize risk scenarios is ...
Question 81: Which of the following risk scenarios would be the GREATEST ...
Question 82: Which of the following would be- MOST helpful to understand ...
Question 83: An internal audit report reveals that not all IT application...
Question 84: Which of the following is the MOST important factor affectin...
Question 85: When reviewing a business continuity plan (BCP). which of th...
Question 86: Which of the following could BEST detect an in-house develop...
Question 87: Which of the following BEST indicates whether security aware...
Question 88: Which of the following activities would BEST contribute to p...
Question 89: Which of the following is the MAIN reason to continuously mo...
Question 90: An organization has procured a managed hosting service and j...
Question 91: Which of the following criteria is MOST important when devel...
Question 92: Which of the following is the MOST useful indicator to measu...
Question 93: Which of the following is the MOST important information to ...
Question 94: Which of the following provides the BEST measurement of an o...
Question 95: Which of the following MUST be updated to maintain an IT ris...
Question 96: An organization has granted a vendor access to its data in o...
Question 97: Which of the following BEST indicates the efficiency of a pr...
Question 98: The BEST way to obtain senior management support for investm...
Question 99: Which of the following would BEST enable a risk practitioner...
Question 100: An organization has initiated a project to implement an IT r...
Question 101: Which of the following aspects of an IT risk and control sel...
Question 102: When testing the security of an IT system, il is MOST import...
Question 103: Which of The following is the BEST way to confirm whether ap...
Question 104: The BEST criteria when selecting a risk response is the:...
Question 105: The PRIMARY benefit of classifying information assets is tha...
Question 106: When reviewing management's IT control self-assessments, a r...
Question 107: An organization is increasingly concerned about loss of sens...
1 commentQuestion 108: Performing a background check on a new employee candidate be...
Question 109: Which of the following is the FIRST step in managing the sec...
Question 110: Which of the following is the BEST method for assessing cont...
Question 111: To minimize risk in a software development project, when is ...
Question 112: A risk practitioner has observed that there is an increasing...
Question 113: Which of the following is MOST appropriate to prevent unauth...
Question 114: Which of the following should be the PRIMARY focus of a risk...
Question 115: Which of the following is the MOST important enabler of effe...
Question 116: Which of the following is MOST important when developing key...
Question 117: A data processing center operates in a jurisdiction where ne...
Question 118: Which of the following is MOST helpful to review when identi...
Question 119: Which of the following risk register elements is MOST likely...
Question 120: Which of the following should be the PRIMARY consideration w...
Question 121: After migrating a key financial system to a new provider, it...
Question 122: Which of the following would MOST likely cause a risk practi...
Question 123: The risk associated with data loss from a website which cont...
Question 124: Which of the following is MOST critical to the design of rel...
Question 125: Which of the following is a risk practitioner's BEST course ...
Question 126: Which of the following would be MOST helpful to a risk owner...
Question 127: Which of the following would provide the MOST comprehensive ...
Question 128: An organization has initiated a project to launch an IT-base...
Question 129: Which of the following is MOST important to include in a Sof...
Question 130: A department has been granted an exception to bypass the exi...
Question 131: The PRIMARY reason to have risk owners assigned to entries i...
Question 132: Which of the following MUST be assessed before considering r...
Question 133: Which of the following is the MOST effective control to ensu...
Question 134: What is the BEST information to present to business control ...
Question 135: Which of the following should be of GREATEST concern to a ri...
Question 136: When developing a new risk register, a risk practitioner sho...
Question 137: Which of the following is a KEY outcome of risk ownership?...
Question 138: An organization has just implemented changes to close an ide...
Question 139: Which of the following controls will BEST detect unauthorize...
Question 140: During the risk assessment of an organization that processes...
Question 141: An organization is planning to outsource its payroll functio...
Question 142: Who is BEST suited to determine whether a new control proper...
Question 143: Periodically reviewing and updating a risk register with det...
Question 144: The PRIMARY reason a risk practitioner would be interested i...
Question 145: A control owner has completed a year-long project To strengt...
Question 146: An organization uses a vendor to destroy hard drives. Which ...
Question 147: What should a risk practitioner do FIRST upon learning a ris...
Question 148: Which of the following is the BEST way to identify changes t...
Question 149: Which of the following is MOST helpful in aligning IT risk w...
Question 150: Which of the following is the MOST important consideration w...
Question 151: A business unit has decided to accept the risk of implementi...
Question 152: Deviation from a mitigation action plan's completion date sh...
Question 153: The PRIMARY benefit of conducting continuous monitoring of a...
Question 154: It is MOST important to the effectiveness of an IT risk mana...
Question 155: Which of the following will BEST help in communicating strat...
Question 156: An organizations chief technology officer (CTO) has decided ...
Question 157: Which of the following is the MOST important consideration w...
Question 158: Which of the following is MOST important when developing key...
Question 159: Which of the following is the MOST important objective of re...
Question 160: Which of the following is the MOST common concern associated...
Question 161: An organization is considering allowing users to access comp...
Question 162: Which of the following is the MOST important benefit of key ...
Question 163: Which of the following is the BEST way to determine the ongo...
Question 164: The purpose of requiring source code escrow in a contractual...
Question 165: Which of the following should be the MAIN consideration when...
Question 166: Which of the following is the BEST method to identify unnece...
Question 167: Risk aggregation in a complex organization will be MOST succ...
Question 168: Which of the following should be considered FIRST when asses...
Question 169: A payroll manager discovers that fields in certain payroll r...
Question 170: Which of the following is the BEST evidence that a user acco...
Question 171: An organization's IT infrastructure is running end-of-life s...
Question 172: An audit reveals that there are changes in the environment t...
Question 173: Which of the following is the BEST method to ensure a termin...
Question 174: An organization has identified a risk exposure due to weak t...
Question 175: A control for mitigating risk in a key business area cannot ...
Question 176: A newly enacted information privacy law significantly increa...
Question 177: Which of the following will BEST help mitigate the risk asso...
Question 178: The PRIMARY reason for periodically monitoring key risk indi...
Question 179: An organization has outsourced its backup and recovery proce...
Question 180: Which of the following BEST indicates the condition of a ris...
Question 181: During a routine check, a system administrator identifies un...
Question 182: Which of the following is the MOST important data attribute ...
Question 183: Which of the following is MOST essential for an effective ch...
Question 184: Which of the following is the FIRST step in managing the ris...
Question 185: Which of the following provides the MOST helpful information...
Question 186: Which of the following should be an element of the risk appe...
Question 187: Which of the following would provide the BEST guidance when ...
Question 188: An organization with a large number of applications wants to...
Question 189: Which of the following is MOST important to review when dete...
Question 190: A risk heat map is MOST commonly used as part of an IT risk ...
Question 191: Which of the following is the MAIN benefit of involving stak...
Question 192: A risk practitioner has become aware of production data bein...
Question 193: Which of the following would BEST help secure online financi...
Question 194: The BEST key performance indicator (KPI) for monitoring adhe...
Question 195: Which of these documents is MOST important to request from a...
Question 196: An organization has received notification that it is a poten...
Question 197: Which of the following provides The BEST information when de...
Question 198: The maturity of an IT risk management program is MOST influe...
Question 199: What is MOST important for the risk practitioner to understa...
Question 200: Which of the following is the MOST effective way to integrat...
Question 201: Which of The following is the PRIMARY consideration when est...
Question 202: Which of the following resources is MOST helpful when creati...
Question 203: Which of the following is the PRIMARY reason for an organiza...
Question 204: Which of the following is the MOST important responsibility ...
Question 205: Which of the following is the BEST control to detect an adva...
Question 206: Which of the following is the BEST method for identifying vu...
Question 207: Which of the following is the BEST approach for determining ...
Question 208: An organization is measuring the effectiveness of its change...
Question 209: Which of the following is MOST important for a risk practiti...
Question 210: The BEST way to demonstrate alignment of the risk profile wi...
Question 211: Which of the following would BEST ensure that identified ris...
Question 212: Which of the following is the PRIMARY benefit of identifying...
Question 213: An organization has recently updated its disaster recovery p...
Question 214: Which of the following will BEST help to ensure that informa...
Question 215: Which of the following is the MOST important consideration w...
Question 216: A risk practitioner is reporting on an increasing trend of r...
Question 217: During the control evaluation phase of a risk assessment, it...
Question 218: In an organization with a mature risk management program, wh...
Question 219: Which of the following should be management's PRIMARY consid...
Question 220: Which of the following is the MOST important characteristic ...
Question 221: Which of the following is the BEST course of action when ris...
Question 222: A control owner identifies that the organization's shared dr...
Question 223: Which of the following is the BEST indication of an improved...
Question 224: Which of the following would be considered a vulnerability?...
Question 225: Prior to selecting key performance indicators (KPIs), itis M...
Question 226: An identified high probability risk scenario involving a cri...
Question 227: After the review of a risk record, internal audit questioned...
Question 228: Which of the following is MOST important when defining contr...
Question 229: Which of the following would MOST likely result in updates t...
Question 230: Which of the following is the MOST important consideration w...
Question 231: A global organization is planning to collect customer behavi...
Question 232: What should be the PRIMARY objective for a risk practitioner...
Question 233: Which of the following would BEST help identify the owner fo...
Question 234: Quantifying the value of a single asset helps the organizati...
Question 235: Which of the following methods is the BEST way to measure th...
Question 236: A risk assessment has identified increased losses associated...