Valid CRISC Dumps shared by ExamDiscuss.com for Helping Passing CRISC Exam! ExamDiscuss.com now offer the newest CRISC exam dumps, the ExamDiscuss.com CRISC exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CRISC dumps with Test Engine here:

Access CRISC Dumps Premium Version
(1745 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 3/225

When updating a risk register with the results of an IT risk assessment, the risk practitioner should log:

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (225q)
Question 1: Which of the following is MOST important for a risk practiti...
Question 2: Which of the following will BEST ensure that information sec...
Question 3: When updating a risk register with the results of an IT risk...
Question 4: A risk practitioner observes that the fraud detection contro...
Question 5: Which of the following is MOST important for developing effe...
Question 6: The design of procedures to prevent fraudulent transactions ...
Question 7: Which of the following would be considered a vulnerability?...
Question 8: An organizations chief technology officer (CTO) has decided ...
Question 9: An organization with a large number of applications wants to...
Question 10: Which of the following provides the MOST helpful reference p...
Question 11: Which of the following is the PRIMARY objective of providing...
Question 12: The head of a business operations department asks to review ...
Question 13: An organization has decided to implement an emerging technol...
Question 14: Which of the following is the BEST measure of the effectiven...
Question 15: Which of the following would be MOST helpful to a risk owner...
Question 16: A monthly payment report is generated from the enterprise re...
Question 17: When reviewing a risk response strategy, senior management's...
Question 18: Following a significant change to a business process, a risk...
1 commentQuestion 19: Which of the following provides the BEST measurement of an o...
Question 20: Who is MOST likely to be responsible for the coordination be...
Question 21: Periodically reviewing and updating a risk register with det...
Question 22: Which of the following can be used to assign a monetary valu...
Question 23: After undertaking a risk assessment of a production system, ...
Question 24: Which of the following would be MOST helpful to an informati...
Question 25: Which of the following is the MOST important requirement for...
Question 26: Which of the following is MOST important for a risk practiti...
Question 27: The BEST metric to monitor the risk associated with changes ...
Question 28: A management team is on an aggressive mission to launch a ne...
Question 29: Which of the following is MOST essential for an effective ch...
Question 30: An external security audit has reported multiple findings re...
Question 31: Implementing which of the following controls would BEST redu...
Question 32: The BEST way to obtain senior management support for investm...
Question 33: Which of the following is the MOST effective way to help ens...
Question 34: A control owner identifies that the organization's shared dr...
Question 35: Deviation from a mitigation action plan's completion date sh...
Question 36: Calculation of the recovery time objective (RTO) is necessar...
Question 37: The GREATEST concern when maintaining a risk register is tha...
Question 38: Who should be accountable for monitoring the control environ...
Question 39: Which of the following will MOST improve stakeholders' under...
Question 40: Which of the following would be of GREATEST concern to a ris...
Question 41: The FIRST task when developing a business continuity plan sh...
Question 42: A control for mitigating risk in a key business area cannot ...
Question 43: IT stakeholders have asked a risk practitioner for IT risk p...
Question 44: Which of the following is MOST critical to the design of rel...
Question 45: Which of the following BEST facilitates the development of e...
Question 46: Which of the following provides The BEST information when de...
Question 47: When reviewing a report on the performance of control proces...
Question 48: Which of the following is the MAIN reason for documenting th...
Question 49: During an IT department reorganization, the manager of a ris...
Question 50: Management has required information security awareness train...
Question 51: Risk aggregation in a complex organization will be MOST succ...
Question 52: Which of the following is the GREATEST benefit to an organiz...
Question 53: The MOST essential content to include in an IT risk awarenes...
Question 54: Which of the following is a KEY responsibility of the second...
Question 55: Which of the following is the BEST approach for determining ...
Question 56: Which of the following BEST indicates that an organization h...
Question 57: Which of the following is MOST helpful in developing key ris...
Question 58: Which of the following would be the BEST key performance ind...
Question 59: What is the GREATEST concern with maintaining decentralized ...
Question 60: Which of the following is MOST important when developing key...
Question 61: The PRIMARY reason for periodic penetration testing of Inter...
Question 62: Which of the following is the PRIMARY role of a data custodi...
Question 63: A risk practitioner discovers several key documents detailin...
Question 64: Which of the following risk register updates is MOST importa...
Question 65: Which of the following will BEST mitigate the risk associate...
Question 66: Which of the following is the MOST important characteristic ...
Question 67: The PRIMARY reason for establishing various Threshold levels...
Question 68: An organization that has been the subject of multiple social...
Question 69: Which of the following will BEST help an organization evalua...
Question 70: An organization has received notification that it is a poten...
Question 71: Which of the following is the MOST important consideration w...
Question 72: The PRIMARY basis for selecting a security control is:...
Question 73: A key risk indicator (KRI) indicates a reduction in the perc...
Question 74: An organization's financial analysis department uses an in-h...
Question 75: Which of the following is the BEST evidence that risk manage...
Question 76: After a risk has been identified, who is in the BEST positio...
Question 77: Which of the following is the BEST key performance indicator...
Question 78: Reviewing which of the following provides the BEST indicatio...
Question 79: To help ensure all applicable risk scenarios are incorporate...
Question 80: Read" rights to application files in a controlled server env...
Question 81: Which of the following is the PRIMARY factor in determining ...
Question 82: Implementing which of the following will BEST help ensure th...
Question 83: A business manager wants to leverage an existing approved ve...
Question 84: A company has located its computer center on a moderate eart...
Question 85: A key risk indicator (KRI) threshold has reached the alert l...
Question 86: Which of the following observations would be GREATEST concer...
Question 87: Who is BEST suited to determine whether a new control proper...
Question 88: When assessing the maturity level of an organization's risk ...
Question 89: Which of the following helps ensure compliance with a nonrep...
Question 90: Which of the following would be MOST helpful when estimating...
Question 91: From a business perspective, which of the following is the M...
Question 92: It is MOST appropriate for changes to be promoted to product...
Question 93: Which of the following is the BEST approach to use when crea...
Question 94: Which of the following BEST enables a proactive approach to ...
Question 95: An organization uses a vendor to destroy hard drives. Which ...
Question 96: A risk practitioner notices that a particular key risk indic...
Question 97: Which of the following would be MOST important for a risk pr...
Question 98: The PRIMARY purpose of a maturity model is to compare the:...
Question 99: Which of the following would provide the MOST comprehensive ...
Question 100: Which of the following controls will BEST detect unauthorize...
Question 101: A risk practitioner has determined that a key control does n...
Question 102: The PRIMARY purpose of using control metrics is to evaluate ...
Question 103: A contract associated with a cloud service provider MUST inc...
Question 104: During a control review, the control owner states that an ex...
Question 105: Which of the following is the BEST key performance indicator...
Question 106: Before implementing instant messaging within an organization...
Question 107: What can be determined from the risk scenario chart? (Exhibi...
Question 108: Which of the following BEST describes the role of the IT ris...
Question 109: Which of the following is the BEST course of action when ris...
Question 110: An internal audit report reveals that not all IT application...
Question 111: When testing the security of an IT system, il is MOST import...
Question 112: Which of the following is the BEST way to determine software...
Question 113: The acceptance of control costs that exceed risk exposure is...
Question 114: Which of the following is the BEST way to support communicat...
Question 115: A recent internal risk review reveals the majority of core I...
Question 116: From a risk management perspective, the PRIMARY objective of...
Question 117: An IT organization is replacing the customer relationship ma...
Question 118: Which of the following should be a risk practitioner s MOST ...
Question 119: Which of the following is the MOST important information to ...
Question 120: Which of the following would be MOST useful when measuring t...
Question 121: When collecting information to identify IT-related risk, a r...
Question 122: Which of the following should a risk practitioner do FIRST w...
Question 123: Prudent business practice requires that risk appetite not ex...
Question 124: Which of the following IT controls is MOST useful in mitigat...
Question 125: When updating the risk register after a risk assessment, whi...
Question 126: Which of the following will BEST help an organization select...
Question 127: Which of The following is the MOST relevant information to i...
Question 128: An organization has granted a vendor access to its data in o...
Question 129: Which of the following is the GREATEST concern associated wi...
Question 130: An organization is increasingly concerned about loss of sens...
Question 131: The BEST criteria when selecting a risk response is the:...
Question 132: A control owner has completed a year-long project To strengt...
Question 133: Which of the following risk management practices BEST facili...
Question 134: During the initial risk identification process for a busines...
Question 135: Which of the following is the BEST indication of an effectiv...
Question 136: The risk associated with an asset before controls are applie...
Question 137: The MOST important reason to aggregate results from multiple...
Question 138: The maturity of an IT risk management program is MOST influe...
Question 139: Which of the following is a crucial component of a key risk ...
Question 140: Which of the following would MOST likely cause a risk practi...
Question 141: Which of the following is the PRIMARY purpose of periodicall...
Question 142: Which of the following should be the PRIMARY consideration w...
Question 143: What is the PRIMARY reason to periodically review key perfor...
Question 144: Which of the following is the MOST important data source for...
Question 145: Which of the following is the BEST metric to demonstrate the...
Question 146: The number of tickets to rework application code has signifi...
Question 147: An organization has introduced risk ownership to establish c...
Question 148: A risk practitioner has observed that there is an increasing...
Question 149: Risk mitigation procedures should include:...
Question 150: Which of The following would offer the MOST insight with reg...
Question 151: Which of the following BEST contributes to the implementatio...
Question 152: Which of the following should be an element of the risk appe...
Question 153: Which of the following will BEST help to ensure that informa...
Question 154: Which of the following provides The MOST useful information ...
Question 155: Which of the following would BEST enable mitigation of newly...
Question 156: Which of the following BEST enables the risk profile to serv...
Question 157: Which of the following is the BEST way to detect zero-day ma...
Question 158: Which of the following elements of a risk register is MOST l...
Question 159: Which of the following is MOST influential when management m...
Question 160: Which of the following is the MOST important consideration w...
Question 161: To help identify high-risk situations, an organization shoul...
Question 162: Which of the following is MOST useful when communicating ris...
Question 163: Which of the following is an IT business owner's BEST course...
Question 164: What is MOST important for the risk practitioner to understa...
Question 165: An organization is planning to engage a cloud-based service ...
Question 166: An application owner has specified the acceptable downtime i...
Question 167: From a risk management perspective, which of the following i...
Question 168: An unauthorized individual has socially engineered entry int...
Question 169: Controls should be defined during the design phase of system...
Question 170: Which of the following is the BEST course of action to reduc...
Question 171: The BEST way to improve a risk register is to ensure the reg...
Question 172: Which of the following is the PRIMARY reason for monitoring ...
Question 173: Participants in a risk workshop have become focused on the f...
Question 174: A risk practitioner learns that the organization s industry ...
Question 175: Which of the following will BEST help ensure that risk facto...
Question 176: An organization has raised the risk appetite for technology ...
Question 177: Which of the following is MOST important to the integrity of...
Question 178: What is the BEST information to present to business control ...
Question 179: Which of the following is MOST important for an organization...
Question 180: Which of the following is MOST important for an organization...
Question 181: A risk practitioner is summarizing the results of a high-pro...
Question 182: IT risk assessments can BEST be used by management:...
Question 183: Which of the following is the PRIMARY benefit of using an en...
Question 184: Sensitive data has been lost after an employee inadvertently...
Question 185: Risk management strategies are PRIMARILY adopted to:...
Question 186: Which of the following is MOST important to review when dete...
Question 187: Which of the following is the BEST way to identify changes t...
Question 188: Which of the following is the MOST effective key performance...
Question 189: A new regulator/ requirement imposes severe fines for data l...
Question 190: Which of the following would BEST help to ensure that suspic...
Question 191: Which of the following is of GREATEST concern when uncontrol...
Question 192: Which of the following is the MAIN reason for analyzing risk...
Question 193: Which of the following would be MOST useful to senior manage...
Question 194: A risk practitioner is reporting on an increasing trend of r...
Question 195: Which of the following would BEST help secure online financi...
Question 196: IT disaster recovery point objectives (RPOs) should be based...
Question 197: Which of the following provides the MOST up-to-date informat...
Question 198: Which of the following is the PRIMARY reason to perform ongo...
Question 199: A risk heat map is MOST commonly used as part of an IT risk ...
Question 200: Which of the following is the PRIMARY reason to have the ris...
Question 201: Which of the following BEST measures the efficiency of an in...
Question 202: In addition to the risk register, what should a risk practit...
Question 203: Which of the following would provide the BEST guidance when ...
Question 204: Which of the following is the BEST indication of the effecti...
Question 205: For no apparent reason, the time required to complete daily ...
Question 206: An organization operates in an environment where reduced tim...
Question 207: Which of the following is MOST important for a risk practiti...
Question 208: Which of the following would be MOST helpful to a risk pract...
Question 209: Which of the following would MOST likely drive the need to r...
Question 210: Which of the following is the PRIMARY responsibility of the ...
Question 211: An audit reveals that there are changes in the environment t...
Question 212: Which of the following changes would be reflected in an orga...
Question 213: A risk practitioner is assisting with the preparation of a r...
Question 214: Of the following, who should be responsible for determining ...
Question 215: Which of the following is the PRIMARY reason to establish th...
Question 216: Which of the following is MOST helpful to review when identi...
Question 217: Which of the following should be management's PRIMARY consid...
Question 218: An organization is considering allowing users to access comp...
Question 219: Which of the following is the MOST critical element to maxim...
Question 220: Which of the following is the MOST important factor when dec...
Question 221: An organization has identified that terminated employee acco...
Question 222: When reviewing a business continuity plan (BCP). which of th...
Question 223: The MAIN purpose of conducting a control self-assessment (CS...
Question 224: Which of the following is the GREATEST advantage of implemen...
Question 225: Which of the following would be a risk practitioner'$ BEST r...