Valid COBIT-Design-and-Implementation Dumps shared by EduDump.com for Helping Passing COBIT-Design-and-Implementation Exam! EduDump.com now offer the newest COBIT-Design-and-Implementation exam dumps, the EduDump.com COBIT-Design-and-Implementation exam questions have been updated and answers have been corrected get the newest EduDump.com COBIT-Design-and-Implementation dumps with Test Engine here:
Which of the following is the BEST approach when developing an EGIT implementation program plan?
Correct Answer: B
When developing an EGIT (Enterprise Governance of IT) implementation program plan, the best approach is to select projects that are high-benefit and relatively easy to implement first. This approach, often referred to as "low-hanging fruit," helps build momentum, demonstrate value quickly, and secure buy-in from stakeholders for more complex initiatives. References in COBIT 2019 Design and Implementation: COBIT 2019 Implementation Guide, Chapter 5:This chapter outlines the importance of prioritizing projects that can deliver quick wins to maintain stakeholder support and demonstrate the value of the governance framework. COBIT 2019 Framework: Governance and Management Objectives, BAI01 (Managed Programs):This objective discusses the prioritization of initiatives based on their potential benefits and implementation feasibility. By focusing on high-benefit, easy-to-implement projects, enterprises can create a solid foundation for more challenging initiatives and ensure continuous progress in their governance implementation efforts.