Valid CISM Dumps shared by EduDump.com for Helping Passing CISM Exam! EduDump.com now offer the newest CISM exam dumps, the EduDump.com CISM exam questions have been updated and answers have been corrected get the newest EduDump.com CISM dumps with Test Engine here:
Which of the following should an information security manager do FIRST when developing an organization's disaster recovery plan (DRP)?
Correct Answer: D
The Business Impact Analysis (BIA) is the first step in developing a disaster recovery plan because it identifies critical business processes, dependencies, and acceptable downtime. "A BIA provides the foundation for disaster recovery planning by identifying business functions and their criticality." - CISM Review Manual 15th Edition, Chapter 3: Program Development, Section: Disaster Recovery Planning* Risk assessments follow the BIA and inform recovery strategies, but the BIA must come first.