All risk management activities are PRIMARILY designed to reduce impacts to:
Correct Answer: B
Explanation The aim of risk management is to reduce impacts to an acceptable level. "Acceptable" or "reasonable" are relative terms that can vary based on environment and circumstances. A minimum level that is consistent with regulatory requirements may not be consistent with business objectives, and regulators typically do not assign risk levels. The minimum level possible may not be aligned with business requirements.