Valid CISA Dumps shared by ExamDiscuss.com for Helping Passing CISA Exam! ExamDiscuss.com now offer the newest CISA exam dumps, the ExamDiscuss.com CISA exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CISA dumps with Test Engine here:
The use of risk assessment tools for classifying risk factors should be formalized in your IT audit effort through:
Correct Answer: D
Section: Protection of Information Assets Explanation: A successful risk-based IT audit program could be based on an effective scoring system. In establishing a scoring system, management should consider all relevant risk factors and avoid subjectivity. Auditors should develop written guidelines on the use of risk assessment tools and risk factors and review these guidelines with the audit committee.