A manager of a project was not able to implement all audit recommendations by the target date. The IS auditor should:
Correct Answer: C
It is important to evaluate what the exposure would be when audit recommendations have not been completed by the target date. Based on the evaluation, management can accordingly consider compensating controls, risk acceptance, etc. All other choicesmight be appropriate only after the risks have been assessed.