Valid CGEIT Dumps shared by ExamDiscuss.com for Helping Passing CGEIT Exam! ExamDiscuss.com now offer the newest CGEIT exam dumps, the ExamDiscuss.com CGEIT exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CGEIT dumps with Test Engine here:
Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than what was originally planned. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes to the project management plan accordingly. What type of risk response has been used in this instance?