Valid CBAP Dumps shared by ExamDiscuss.com for Helping Passing CBAP Exam! ExamDiscuss.com now offer the newest CBAP exam dumps, the ExamDiscuss.com CBAP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CBAP dumps with Test Engine here:
A business analyst (BA) is reviewing the performance results from a recent change initiative. One of the results stated, "The planned schedule expected 50% of the project to be done at milestone 6. The schedule performance index (SPI) was .87. Three project team members worked overtime to ensure that the actual schedule would align with the planned schedule." This is an example of what type of action?