Regarding the four disaster recovery modes of HyperMetro, Hot Standby, Warm Standby, and Cold Standby, is the following statement wrong?
Correct Answer: B
Explanation
Analysis: The warm standby technology is implemented on the basis of the active and standby data centers, provided that there are two active and standby data centers.
The standby data center is deployed for warm standby, and application services are responded to by the primary data center.
When the service is unavailable, it is necessary to realize the overall switching of the data center within the specified RTO time. When realizing the main data When the center switches, it is necessary to disconnect the main data center routing link and connect the backup data center routing link to ensure the same time There is only one data center online. The warm-up technology is still a manual method, and someone needs to be on duty 24 hours to complete the operation.
The work effect is low.