Explanation:
To set up HPE Synergy frames after the hardware components are discovered within HPE OneView, the following steps should be followed in the correct order:
* Create an enclosure group.
* Create a logical interconnect group with uplink sets.
* Define all required networks.
* Create a logical enclosure.
* Create server profile templates and server profiles.
* Create an enclosure group:This step involves defining the enclosure group, which includes the configurations for the enclosure such as firmware baselines and logical interconnect groups.
* Create a logical interconnect group with uplink sets:Next, set up the logical interconnect group, which includes the uplink sets that define the connectivity from the enclosures to the data center networks.
* Define all required networks:After setting up the logical interconnect group, define all the necessary networks that will be used within the HPE Synergy environment.
* Create a logical enclosure:Create a logical enclosure by combining the physical enclosures with the
* defined enclosure group, effectively binding the hardware configuration with the logical settings.
* Create server profile templates and server profiles:Finally, create server profile templates and individual server profiles to apply the required configuration settings to the compute modules.