Question 392/412

How is the schedule variance calculated using the earned value technique?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (412q)
Question 1: Specification of both the deliverables and the processes is ...
Question 2: At the completion of a project, a report is prepared that de...
Question 3: Which process involves subdividing project deliverables and ...
Question 4: Which of the following includes how requirements activities ...
Question 5: At which point of the project is the uncertainty the highest...
Question 6: Which of the following is an input to the Direct and Manage ...
Question 7: Which grid shows which resources are tied to work packages?...
Question 8: Power, urgency, and legitimacy are attributes of which stake...
Question 9: An example of a group decision-making technique is:...
Question 10: Which is the Define Scope technique used to generate differe...
Question 11: Plan Risk Management is the process of defining how to:...
Question 12: The item that provides more detailed descriptions of the com...
Question 13: Which of the following techniques is used during Control Sco...
Question 14: The scope management plan and scope baseline are contained i...
Question 15: The formal and informal interaction with others in an organi...
Question 16: The project management processes presented in the PMBOK Guid...
Question 17: Which process documents the business needs of a project and ...
Question 18: y cost estimates are quantitative assessments of the probabl...
Question 19: Units of measure, level of precision, level of accuracy, con...
Question 20: The process of formalizing acceptance of the completed proje...
Question 21: Which process determines the risks that may affect the proje...
Question 22: Projects are separated into phases or subprojects; these pha...
Question 23: Which tool or technique is used in the Estimate Costs proces...
Question 24: Which type of chart is a graphic representation of a process...
Question 25: The scope of a project cannot be defined without some basic ...
Question 26: Inputs to the Plan Risk Management process include the:...
Question 27: The following is a network diagram for a project. (Exhibit) ...
Question 28: Which statement is true about the project management body of...
Question 29: What type of planning is used where the work to be accomplis...
Question 30: What causes replanning of the project scope?...
Question 31: A project has a current cost performance index (CPI) of 1.25...
Question 32: Which technique is used in Perform Quantitative Risk Analysi...
Question 33: A work package has been scheduled to cost $1,000 to complete...
Question 34: Which schedule compression technique has phases or activitie...
Question 35: Which baselines make up the performance measurement baseline...
Question 36: In the Estimate Activity Durations process, productivity met...
Question 37: Which is an output of the Collect Requirements process?...
Question 38: A change log for communications can be used to communicate t...
Question 39: The purpose of the Project Communications Management Knowled...
Question 40: A project manager has created an issue log to document issue...
Question 41: After Define Activities and Sequence Activities, the next pr...
Question 42: Which cost is associated with nonconformance?...
Question 43: Which output is the approved version of the time-phased proj...
Question 44: Which process identifies whether the needs of a project can ...
Question 45: Which Define Activities output extends the description of th...
Question 46: What are the formal and informal policies, procedures, and g...
Question 47: Which document includes the project scope, major deliverable...
Question 48: Which defines the portion of work included in a contract for...
Question 49: What are the identified risks for doing excessive decomposit...
Question 50: In which Knowledge Area is the project charter developed?...
Question 51: Which of the following is an output of the Distribute Inform...
Question 52: What is the probability of occurrence if the risk rating is ...
Question 53: How should a stakeholder who is classified as high power and...
Question 54: Which of the Perform Quality Assurance tools and techniques ...
Question 55: Cost baseline is an output of which of the following process...
Question 56: In the basic communication model, which term refers to the m...
Question 57: The ways in which the roles and responsibilities, reporting ...
Question 58: Processes in the Initiating Process Group may be completed a...
Question 59: An output of the Develop Project Team process is:...
Question 60: Which tool and technique is used in Conduct Procurements?...
Question 61: A regression line is used to estimate:...
Question 62: Which of the following is a tool or technique of the Define ...
Question 63: Which earned value management (EVM) metric is a measure of t...
Question 64: An output of the Plan Quality Management process is:...
Question 65: High-level project risks are included in which document?...
Question 66: When calculating the cost of quality (COQ) for a product or ...
Question 67: The degree of uncertainty an entity is willing to take on in...
Question 68: Which of the following is an output of the Define Activities...
Question 69: An input to Conduct Procurements is:...
Question 70: Which of the seven basic quality tools is especially useful ...
Question 71: Which process occurs within the Monitoring and Controlling P...
Question 72: What tool and technique is used to determine whether work an...
Question 73: Status of deliverables, implementation status for change req...
Question 74: One of the objectives of a quality audit is to:...
Question 75: A reward can only be effective if it is:...
Question 76: Which tools or techniques will a project manager use for Dev...
Question 77: Retreating from an actual or potential conflict or postponin...
Question 78: Which process involves identifying and documenting the logic...
Question 79: Which Collect Requirements output links the product requirem...
Question 80: In project management, a temporary project can be:...
Question 81: Which of the following is an example of the simplest fixed-p...
Question 82: Which Process Group typically consumes the bulk of a project...
Question 83: During which process does the project team receive bids and ...
Question 84: Funding limit reconciliation is a tool and technique used in...
Question 85: The number of potential communication channels for a project...
Question 86: Which process determines the risks that might affect the pro...
Question 87: Which Process Group and Knowledge Area include the Sequence ...
Question 88: Which of the following is a tool or technique used in the Ac...
Question 89: In the Develop Project Team process, which of the following ...
Question 90: As part of a mid-project evaluation, the project sponsor has...
Question 91: Which technique is utilized in the Control Schedule process?...
Question 92: The following is a network diagram for a project. (Exhibit) ...
Question 93: A procurement management plan is a subsidiary of which other...
Question 94: A collection of projects managed as a group to achieve strat...
Question 95: Which is a tool or technique used in Define Scope?...
Question 96: Which process in Project Time Management includes reserve an...
Question 97: Which Knowledge Areas include processes from the Closing Pro...
Question 98: Which of the following is a project constraint?...
Question 99: The component of the human resource management plan that inc...
Question 100: The probability and impact matrix is primarily used to:...
Question 101: Reserve analysis is a tool and technique used in which proce...
Question 102: Work performance information and cost forecasts are outputs ...
Question 103: Conditions that are not under the control of the project tea...
Question 104: Which of the following terms indicates a deliverable-oriente...
Question 105: Which process uses occurrence probability and impact on proj...
Question 106: Which tool or technique is required in order to determine th...
Question 107: Organizational planning impacts projects by means of project...
Question 108: The Human Resource Management processes are:...
Question 109: At which stage of team development do members begin to work ...
Question 110: Which of the following is an input to the Develop Project Ch...
Question 111: An input to the Perform Quantitative Risk Analysis process i...
Question 112: Which process is included in the Project Integration Managem...
Question 113: Changes to formally controlled documentation, plans, etc. to...
Question 114: What is an objective of the Develop Project Team process?...
Question 115: The completion of the project scope is measured against the:...
Question 116: The purpose of inspection in Perform Quality Control is to k...
Question 117: Which tool or technique is used to develop the human resourc...
Question 118: When large or complex projects are separated into distinct p...
Question 119: Which type of analysis systemically gathers and analyzes qua...
Question 120: An output of Control Schedule is:...
Question 121: Resource calendars are included in the:...
Question 122: Which Perform Quality Control tool graphically represents ho...
Question 123: The processes required to establish the scope of the project...
Question 124: During project selection, which factor is most important?...
Question 125: What is the name of the statistical method that helps identi...
Question 126: Which tool or technique used in the Control Procurements pro...
Question 127: What type of reward can hurt team cohesiveness?...
Question 128: Conflict should be best addressed in which manner?...
Question 129: The group technique that enhances brainstorming with a votin...
Question 130: The process to ensure that appropriate quality standards and...
Question 131: If the most likely duration of an activity is five weeks, th...
Question 132: Sharing good practices introduced or implemented in similar ...
Question 133: Lessons learned are created and project resources are releas...
Question 134: Which component of the human resource management plan descri...
Question 135: Which activity may occur at project or phase closure?...
Question 136: Which process should be conducted from the project inception...
Question 137: What type of project structure is a hierarchically organized...
Question 138: A risk response strategy in which the project team shifts th...
Question 139: What is the function of a Project Management Office (PMO)?...
Question 140: Inputs to the Plan Schedule Management process include:...
Question 141: Requirements documentation will typically contain at least:...
Question 142: What provides information regarding the ways people, teams, ...
Question 143: The planned work contained in the lowest level of work break...
Question 144: Which process includes prioritizing risks for subsequent fur...
Question 145: While processes in the Planning Process Group seek to collec...
Question 146: A temporary endeavor that creates a unique product or servic...
Question 147: Perform Quality Control is accomplished by:...
Question 148: What is the definition of Direct and Manage Project Executio...
Question 149: Quality metrics are an output of which process?...
Question 150: A measure of cost performance that is required to be achieve...
Question 151: An input to the Estimate Activity Resources process is:...
Question 152: Which process involves the creation of a document that provi...
Question 153: Project or phase closure guidelines or requirements, histori...
Question 154: Change requests are an output from which Project Integration...
Question 155: Which of the following involves making information available...
Question 156: Prototype development may be used as a tool for which of the...
Question 157: Which conflict resolution technique searches for solutions t...
Question 158: The project management processes are usually presented as di...
Question 159: Which of the following are an enterprise environmental facto...
Question 160: Which type of estimating can produce higher levels of accura...
Question 161: When does Monitor and Control Risks occur?...
Question 162: Which enterprise environmental factors may influence Plan Sc...
Question 163: When cost variance is negative and schedule variance is posi...
Question 164: Which Control Quality tool is also known as an arrow diagram...
Question 165: The process for performing variance analysis may vary, depen...
Question 166: Updates to organizational process assets such as procurement...
Question 167: Which of the following is an output of the Conduct Procureme...
Question 168: Exhibit A is an example of which of the following types of S...
Question 169: Through whom do project managers accomplish work?...
Question 170: The application of knowledge, skills, tools, and techniques ...
Question 171: An input to the Perform Integrated Change Control process is...
Question 172: A project manager who communicates to the project team thoug...
Question 173: The following is a network diagram for a project. (Exhibit) ...
Question 174: When the business objectives of an organization change, proj...
Question 175: An output of the Manage Stakeholder Engagement process is:...
Question 176: The cost benefit analysis tool is used for creating:...
Question 177: What is the estimate at completion (EAC) if the budget at co...
Question 178: What name(s) is (are) associated with the Plan-Do-Check-Act ...
Question 179: Which type of dependency is contractually required or inhere...
Question 180: The organization's perceived balance between risk taking and...
Question 181: A project manager managing a cross-cultural virtual project ...
Question 182: What happens to a stakeholder's project influence over time?...
Question 183: Which Process Group contains the processes performed to comp...
Question 184: Which item is an output of Plan Quality Management and an in...
Question 185: An output of the Perform Integrated Change Control process i...
Question 186: Which type of contract is a hybrid of both a cost-reimbursab...
Question 187: Processes in the Planning Process Group are typically carrie...
Question 188: Identify Risks is part of which Process Group?...
Question 189: Who determines which dependencies are mandatory during the S...
Question 190: When a permitting agency takes longer than planned to issue ...
Question 191: Which Project Management Process Group includes Collect Requ...
Question 192: A method to manage stakeholder expectations in the scope sta...
Question 193: An input of the Plan Procurement Management process is:...
Question 194: The project manager notes that stakeholders are aware of the...
Question 195: Which tool is used to develop technical details within the p...
Question 196: A project management office manages a number of aspects incl...
Question 197: Which process is responsible for monitoring the status of th...
Question 198: Stakeholders can be identified in later stages of the projec...
Question 199: The three processes of Project Cost Management are:...
Question 200: The product scope description is used to:...
Question 201: A tool and technique used during the Perform Qualitative Ris...
Question 202: Which index is the calculated projection of cost performance...
Question 203: The business needs, assumptions, and constraints and the und...
Question 204: Which type of contract is most commonly used by buying organ...
Question 205: When a project is undertaken to reduce defects in a product ...
Question 206: The Monitoring and Controlling Process Group includes proces...
Question 207: Which type of dependency is established based on knowledge o...
Question 208: Risk responses reflect an organization's perceived balance b...
Question 209: Which type of project management office (PMO) supplies templ...
Question 210: Which piece of information is part of the WBS Dictionary?...
Question 211: Which is one of the determining factors used to calculate CP...
Question 212: Configuration identification, configuration status accountin...
Question 213: A tool and technique used during the Collect Requirements pr...
Question 214: Which Control Scope input is compared to actual results to d...
Question 215: Which risk management strategy seeks to eliminate the uncert...
Question 216: A project manager seeking insight on previous stakeholder ma...
Question 217: A project manager should document the escalation path for un...
Question 218: An input to Close Project or Phase is:...
Question 219: Who is responsible for initiating a project?...
Question 220: Job satisfaction, challenging work, and sufficient financial...
Question 221: To which process is work performance information an input?...
Question 222: A project manager builds consensus and overcomes obstacles b...
Question 223: Which of the following factors is lowest at the start of the...
Question 224: The approaches, tools, and data sources that will be used to...
Question 225: Which of the following is a narrative description of product...
Question 226: The project budget is set at $150,000. The project duration ...
Question 227: Which Process Group's purpose is to track, review, and regul...
Question 228: Payback period, return on investment, internal rate of retur...
Question 229: Which output of Project Cost Management consists of quantita...
Question 230: Which of the following can be used as an input for Define Sc...
Question 231: A weighting system is a tool for which area of Conduct Procu...
Question 232: Which tool or technique can a project manager use to select ...
Question 233: Which item is a cost of conformance?...
Question 234: The component of the risk management plan that documents how...
Question 235: The integrative nature of project management requires which ...
Question 236: Which of the following is an output of Close Procurements?...
Question 237: Which tool or technique is used in the Develop Project Manag...
Question 238: Which techniqe should a project manager use in a situation i...
Question 239: The project scope statement and resource calendars are input...
Question 240: Administer Procurements is part of which Process Group?...
Question 241: The risk shared between the buyer and seller is determined b...
Question 242: Which type of diagram includes groups of information and sho...
Question 243: Activity cost estimates and the project schedule are inputs ...
Question 244: Which process involves documenting the actions necessary to ...
Question 245: An effective technique for resolving conflict that incorpora...
Question 246: Project deliverables that have been completed and checked fo...
Question 247: The process of prioritizing risks for further analysis or ac...
Question 248: The technique of subdividing project deliverables into small...
Question 249: Outputs of the Control Communications process include:...
Question 250: Which tool or technique is used to manage change requests an...
Question 251: The most commonly used type of precedence relationship in th...
Question 252: Which tool or technique of the Define Activities process all...
Question 253: Which of the following is a group decision-making technique?...
Question 254: What is the schedule performance index (SPI) using the follo...
Question 255: Which input to Collect Requirements is used to identify stak...
Question 256: Which of the following are three inputs to the risk register...
Question 257: Which quality tool may prove useful in understanding and est...
Question 258: An input to the Identify Stakeholders process is:...
Question 259: Change requests, project management plan updates, project do...
Question 260: The ability to influence cost is greatest during which stage...
Question 261: The links between the processes in the Process Groups are of...
Question 262: Which Knowledge Area involves identifying the people, groups...
Question 263: In which process might a project manager use risk reassessme...
Question 264: When an activity cannot be estimated with a reasonable degre...
Question 265: Which technique helps to determine the risks that have the m...
Question 266: In which type of contract are the performance targets establ...
Question 267: Which type of analysis is used as a general management techn...
Question 268: Which of the following is a tool or technique used in the De...
Question 269: Which is one of the major outputs of Sequence Activities?...
Question 270: Activity resource requirements and the resource breakdown st...
Question 271: The process of identifying and documenting relationships amo...
Question 272: An input of the Create WBS process is:...
Question 273: Which tool or technique allows a large number of ideas to be...
Question 274: Completion of the product scope is measured against the prod...
Question 275: Which provides the basic framework for managing a project?...
Question 276: Which group creativity technique asks a selected group of ex...
Question 277: One of the tools and techniques of the Manage Project Team p...
Question 278: Sending letters, memos, reports, emails, and faxes to share ...
Question 279: Which basic quality tool explains a change in the dependent ...
Question 280: In which process is a project manager identified and given t...
Question 281: Which activity involves ensuring that the composition of a p...
Question 282: Projects that share common outcomes, collective capability, ...
Question 283: Which Develop Schedule tool and technique produces a theoret...
Question 284: The creation of an internet site to engage stakeholders on a...
Question 285: Which characteristics do effective project managers possess?...
Question 286: What are the Project Procurement Management processes?...
Question 287: A graphic display of project team members and their reportin...
Question 288: Which process numerically analyzes the effect of identified ...
Question 289: The process of identifying and documenting the specific acti...
Question 290: In which domain of project management would a Pareto chart p...
Question 291: Which illustrates the connection between work that needs to ...
Question 292: Which Control Stakeholder Engagement tool or technique allow...
Question 293: Which of the following is a tool and technique used to monit...
Question 294: The following is a network diagram for a project. The shorte...
Question 295: Which degree of authority does a project manager have on a p...
Question 296: Labor, materials, equipment, and supplies are examples of:...
Question 297: An output of the Direct and Manage Project Work process is:...
Question 298: Tools and techniques used in Direct and Manage Project Work ...
Question 299: Definitions of probability and impact, revised stakeholder t...
Question 300: Which of the following change requests can bring expected fu...
Question 301: The stakeholder register is an output of:...
Question 302: The correct equation for schedule variance (SV) is earned va...
Question 303: Managing ongoing production of goods and services to ensure ...
Question 304: The milestone list is an input to which process from the Pla...
Question 305: The process improvement plan details the steps for analyzing...
Question 306: The initial development of a Project Scope Management plan u...
Question 307: Which item is a formal proposal to modify any document, deli...
Question 308: In a project, total float measures the:...
Question 309: Which risk response strategy is common for both positive and...
Question 310: Which statement correctly describes the value of a business ...
Question 311: Which organizational process assets update is performed duri...
Question 312: Which of the following is a statistical concept that calcula...
Question 313: Expected monetary value (EMV) is computed by which equation?...
Question 314: The degree, amount, or volume of risk that an organization o...
Question 315: When should quality planning be performed?...
Question 316: An output of the Create WBS process is:...
Question 317: The procurement process that documents agreements and relate...
Question 318: Typical outcomes of a project include:...
Question 319: The following is a network diagram for a project. (Exhibit) ...
Question 320: Which tool or technique is used in validating the scope of a...
Question 321: The total of the planned value (PV) is also known as:...
Question 322: When can pre-assignment of project team members occur?...
Question 323: An issue log is an input to which Project Human Resource Man...
Question 324: Identify Stakeholders is the process of identifying all of t...
Question 325: What is the name of a graphic display of project team member...
Question 326: The definition of when and how often the risk management pro...
Question 327: Risk categorization is a tool or technique used in which pro...
Question 328: Which of the following statements best describes the influen...
Question 329: When a backward pass is calculated from a schedule constrain...
Question 330: Which type of managers do composite organizations involve?...
Question 331: Which of the following is an output of Define Scope?...
Question 332: The diagram below is an example of a: (Exhibit)...
Question 333: Using the three-point estimating technique, if the most like...
Question 334: Skills necessary for project management such as motivating t...
Question 335: An example of a group decision-making technique is:...
Question 336: Analogous cost estimating relies on which of the following t...
Question 337: Which process involves developing an approximation of the mo...
Question 338: External organizations that have a special relationship with...
Question 339: The zero duration of milestones in project planning occurs b...
Question 340: Which type of manager is assigned by the performing organiza...
Question 341: Which process involves defining, preparing, and coordinating...
Question 342: A strengths, weaknesses, opportunities, and threats (SWOT) a...
Question 343: An input to the Plan Procurement Management process is:...
Question 344: Which type of graphic is displayed below? (Exhibit)...
Question 345: A project lifecycle is defined as:...
Question 346: Which key interpersonal skill of a project manager is define...
Question 347: In Plan Risk Management, which of the management plans deter...
Question 348: A tool or technique used in the Control Procurements process...
Question 349: Which type of dependency used in the Sequence Activities pro...
Question 350: Stakeholder satisfaction should be managed as a key project:...
Question 351: The CPI is .92, and the EV is US$172,500. What is the actual...
Question 352: The individual or group that provides resources and support ...
Question 353: The process of identifying specific actions to be performed ...
Question 354: The project has a current cost performance index of 0.80. As...
Question 355: Identifying major deliverables, deciding if adequate cost es...
Question 356: Which of the following consists of the detailed project scop...
Question 357: What risk technique is used to quantify the probability and ...
Question 358: Which process involves aggregating the estimated costs of th...
Question 359: Which of the following is a set of interrelated actions and ...
Question 360: The staffing management plan is part of the:...
Question 361: In the Plan Stakeholder Management process, expert judgment ...
Question 362: Which type of management focuses on ensuring that projects a...
Question 363: The contract in which the seller is reimbursed for all allow...
Question 364: Which type of analysis is used to examine project results th...
Question 365: The project manager at an organization has just realized tha...
Question 366: Which of the following processes audits the quality requirem...
Question 367: Which of the following is an input to Direct and Manage Proj...
Question 368: Which of the following is a strategy to deal with positive r...
Question 369: When is a project finished?
Question 370: Which is a communication method used in the Report Performan...
Question 371: Which of the following tools and techniques is used in the V...
Question 372: Which of the following response strategies are appropriate f...
Question 373: Which input will be used when tasked with developing the hum...
Question 374: Risk exists the moment that a project is:...
Question 375: A logical relationship in which a successor activity cannot ...
Question 376: A purchase order for a specified item to be delivered by a s...
Question 377: Define Activities and Estimate Activity Resources are proces...
Question 378: Prioritizing risks for further analysis or action by assessi...
Question 379: Which tools or techniques are used during the Close Project ...
Question 380: A tool and technique used during the Define Scope process is...
Question 381: What is project management?
Question 382: Ensuring that both parties meet contractual obligations and ...
Question 383: A project manager at a publishing company decides to initiat...
Question 384: The iterative process of increasing the level of detail in a...
Question 385: Which process requires implementation of approved changes?...
Question 386: Which of the following characteristics are found in a functi...
Question 387: A key benefit of the Manage Communications process is that i...
Question 388: A project requires a component with well-understood specific...
Question 389: Assigned risk ratings are based upon:...
Question 390: When does the project team determine which dependencies are ...
Question 391: Under which type of contract does the seller receive reimbur...
Question 392: How is the schedule variance calculated using the earned val...
Question 393: The basis of identification for current or potential problem...
Question 394: A stakeholder expresses a need not known to the project mana...
Question 395: At the end of the project, what will be the value of SV?...
Question 396: The process of monitoring the status of the project to updat...
Question 397: While preparing the project management plan on a weekly basi...
Question 398: What is one of the objectives of Project Risk Management?...
Question 399: An output of the Create WBS process is:...
Question 400: An electronics firm authorizes a new project to develop a fa...
Question 401: Which of the following documents allows the project manager ...
Question 402: The process of monitoring the status of the project and prod...
Question 403: What is a deliverable-oriented, hierarchical decomposition o...
Question 404: Projects are undertaken by an organization to support the:...
Question 405: Which type of contract gives both the seller and the buyer f...
Question 406: An input to the Collect Requirements process is the:...
Question 407: Sensitivity analysis is typically displayed as a/an:...
Question 408: Which tool or technique is used in the Perform Integrated Ch...
Question 409: Plan-do-check-act is also known as:...
Question 410: Most experienced project managers know that:...
Question 411: Which of the following processes are part of the Project Int...
Question 412: Which of the following is an estimating technique that uses ...