Question 72/84

Which describes a risk effect?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (84q)
Question 1: Which is a true statement about management stages and techni...
Question 2: Which is an objective of the Initiating a Project process?...
Question 3: In which product would you find a product's quality toleranc...
Question 4: Which process is used by a Team Manager to coordinate work o...
Question 5: Which is a purpose of the Quality theme?...
Question 6: What process is used by the Project Board to respond to an E...
Question 7: Which is performed as part of the recommended risk managemen...
Question 8: Which provides a single source of reference that may be used...
Question 9: If Work Package tolerance is forecast to be exceeded, to who...
Question 10: Identify the missing words in the following sentence. A Chan...
Question 11: What theme estimates the cost of delivering the project?...
Question 12: When are tolerances for a Work Package agreed?...
Question 13: Which should be funded by a change budget?...
Question 14: Which activity takes place within the Managing a Stage Bound...
Question 15: What process ensures focus on the delivery of a stage's prod...
Question 16: Which is NOT confirmed during the Initiating a Project proce...
Question 17: Which is one of the six aspects of project performance that ...
Question 18: Which product documents the information needed to demonstrat...
Question 19: Which is a purpose of a Project Brief?...
Question 20: Which role is part of the project management team?...
Question 21: Which is NOT a purpose of a Benefits Review Plan?...
Question 22: Which products, identified when creating a product breakdown...
Question 23: When should the Project Board refer to corporate or programm...
Question 24: Which of the following is NOT an event-driven control?...
Question 25: Which is a purpose of the Starting up a Project process?...
Question 26: Which is a purpose of the Risk theme?...
Question 27: Which is NOT included in the PRINCE2 definition of a project...
Question 28: What product should be used to confirm the version number of...
Question 29: Which is an objective of the Starting up a Project process?...
Question 30: Which is an objective of the Closing a Project process?...
Question 31: Which of the following describes a use of a Configuration It...
Question 32: Why would the Project Manager escalate an issue to the Proje...
Question 33: Why is a Project Brief produced?...
Question 34: What takes place during the Closing a Project process?...
Question 35: Which product records any project outcomes perceived as nega...
Question 36: Which PRINCE2 principle helps to address a concern that the ...
Question 37: Which role does NOT set tolerances?...
Question 38: Which is NOT undertaken during the Initiating a Project proc...
Question 39: What is described as an organization's unique attitude towar...
Question 40: What process aims to ensure accurate progress information is...
Question 41: Which role is responsible for the management of a risk assig...
Question 42: Which is a type of issue?
Question 43: What product is used to maintain a record of those who have ...
Question 44: Which is a purpose of the Plans theme?...
Question 45: Identify the missing word(s) in the following sentence, PRIN...
Question 46: Which is the Change Authority role permitted to authorize?...
Question 47: Where should a Team Manager look for information on the qual...
Question 48: What product identifies the management stages and other majo...
Question 49: Who is the key project decision-maker in the project managem...
Question 50: Which of the following statements about stakeholders are tru...
Question 51: Which task is performed by the Change Authority?...
Question 52: A product can NOT be supplied to meet all of the requirement...
Question 53: Who carries out audits that are independent of the project?...
Question 54: Which risk response type is a recommended response to both a...
Question 55: Which is a purpose of an End Stage Report?...
Question 56: Which of the following statements about the Closing a Projec...
Question 57: Which is a benefit of using PRINCE2?...
Question 58: What is a purpose of a Benefits Review Plan?...
Question 59: Which describes the 'Identify Risks' step within the recomme...
Question 60: Which is one of the three levels of plan in PRINCE2?...
Question 61: Which is a purpose of the Managing Product Delivery process?...
Question 62: Which is NOT a type of issue?
Question 63: What process is used by the Project Manager to maintain focu...
Question 64: Which is a purpose of the Organization theme?...
Question 65: Which statement describes the Implement' step within the rec...
Question 66: Which principle helps to define what should be included and ...
Question 67: Which is a difference between management and technical stage...
Question 68: What is defined as a temporary organization that is created ...
Question 69: What product forms the contract' between the Project Board a...
Question 70: Which is NOT a requirement of a Stage Plan?...
Question 71: Which theme addresses the need to have a strategy for commun...
Question 72: Which describes a risk effect?
Question 73: How many tasks does the product-based planning technique des...
Question 74: Which is NOT a PRINCE2 principle?...
Question 75: Which product is NOT created in the Managing a Stage Boundar...
Question 76: Which product describes the roles and responsibilities for a...
Question 77: What process provides the information required to decide whe...
Question 78: In what product should the quality criteria for a specialist...
Question 79: Identify the missing word in the following sentence, A purpo...
Question 80: Which is a purpose of an Issue Report?...
Question 81: Which is NOT one of the levels of plan recommended by PRINCE...
Question 82: Which is a purpose of a Lessons Report?...
Question 83: Who should act as the communication channel between a projec...
Question 84: Identify the missing words in the following sentence. A prob...