During a Sprint Planning session, the team argues about the work estimates for a particular story.
The Product Owner estimates five days.

The Lead Architect estimates two days.

The Scrum Master estimates eight days.

The team member working on it estimates seven days.

What value (in days) should be used for planning?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (57q)
Question 1: How does Agile bring predictability to the Planning process?...
Question 2: A team estimates a Story using the Planning Poker technique....
Question 3: What is a Scrum-of-Scrums?
Question 4: Who is responsible for implementing the actions agreed upon ...
Question 5: Which of the following statements best expresses the role th...
Question 6: A customer requests a report that summarizes functionality a...
Question 7: Which Scrum ritual is meant to look back and improve upon th...
Question 8: Which is a statement of value as described in the Agile mani...
Question 9: During a Sprint Planning session, the team argues about the ...
Question 10: What is the objective of the Scrum-of-Scrums meeting?...
Question 11: What is an information radiator?...
Question 12: Near the end of a Sprint, the team realizes that they will n...
Question 13: What is time-boxing?
Question 14: The team determines that it has over-committed itself for a ...
Question 15: A team has eleven members spread over two locations across t...
Question 16: What is meant by the velocity of the team?...
Question 17: How should 'done' be defined when multiple teams are working...
Question 18: A story was estimated at eight ideal hours. A working day is...
Question 19: A Scrum team failed to meet the Sprint objectives. One of th...
Question 20: When is a Sprint complete?
Question 21: Which statement describes Release Planning?...
Question 22: Who should update the work estimates during the Sprint?...
Question 23: What is the expected outcome of the first Sprint on a projec...
Question 24: In a Scrum project, when would a requirement get added to th...
Question 25: Why is planning poker an effective estimation technique?...
Question 26: The Product Owner is going on a three-week vacation. The tea...
Question 27: What is the best way to split up teams on a large project wh...
Question 28: What is a Sprint?
Question 29: What should the Scrum Master advise the team to give their m...
Question 30: During the release planning meeting, it is difficult to agre...
Question 31: A user story was estimated at five ideal hours. On a normal ...
Question 32: Who knows most about the progress towards a business objecti...
Question 33: What is the relationship between the Product Backlog, the Re...
Question 34: A team is trying to convince a customer about the value of a...
Question 35: What is a characteristic of a well-designed Agile work space...
Question 36: What is the primary responsibility of a Scrum Master in orde...
Question 37: A team selects a Product Backlog Item (PBI) for the Sprint B...
Question 38: What message can you give to a customer about a key benefit ...
Question 39: Who is the owner of a Sprint Backlog Item during the Sprint ...
Question 40: A Project Manager wants to track not just the rate of progre...
Question 41: A large product team features six different teams having ten...
Question 42: A 200 member project team is working on a large and complex ...
Question 43: Collaboration is the most important parameter for the succes...
Question 44: Sprint planning should result in a commitment on what will b...
Question 45: What is an "escaped defect"?
Question 46: What is the usual length of the time box for the complete Sp...
Question 47: Which means of communication is the most preferable to clari...
Question 48: For a Sprint, progress is monitored in a burn-up chart with ...
Question 49: A Manager requests to attend the daily stand-up meeting so t...
Question 50: Why does the Daily Scrum need to be held at the same locatio...
Question 51: According to Agile principles, what should be the pace of de...
Question 52: From which sport is the term "Scrum" and much of the termino...
Question 53: A team is estimating story points. They estimate that the st...
Question 54: During a Sprint, the team completes four stories with story ...
Question 55: Agile planning happens at multiple levels including a daily ...
Question 56: A team decided to install a large traffic light in the team ...
Question 57: An engineering organization is transforming their project ma...