Valid D-MSS-DS-23 Dumps shared by ExamDiscuss.com for Helping Passing D-MSS-DS-23 Exam! ExamDiscuss.com now offer the newest D-MSS-DS-23 exam dumps, the ExamDiscuss.com D-MSS-DS-23 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com D-MSS-DS-23 dumps with Test Engine here:
A technical architect is helping a customer prepare for a data center maintenance window. All applications must failover to the disaster recovery site. The customer also wants to test their disaster recovery plan. What PowerStore Manager replication option should be used to address the customer's need, and from which site should the option be run?
Correct Answer: B
For a customer preparing for a data center maintenance window and wanting to test their disaster recovery plan, the recommended PowerStore Manager replication option is a planned failover from the source site. This process involves initiating the failover from the source site, ensuring a controlled transition of applications and services to the disaster recovery site. Planned failover allows for testing the disaster recovery plan while maintaining data integrity. Reference:Dell PowerStore Replication Best Practices