An engineer needs to configure a redundant CMC network link into to a newly installed FX2 chassis. CMC port 1 is up and working. The engineer only has one management switch available for CMC connections.
The engineer plugs CMC port 2 into the management switch and leaves the data center. The network engineer reports extreme traffic on the network and is unable to connect to any other switches.
How should the engineer fix this problem quickly and maintain redundancy?