A Linux administrator discovers that a configured schedule is not running properly and needs to re-create the schedule. The task should run every Monday at 13:30 but only during the months of February, May, August, and November. Which of the following options should the administrator use?
Correct Answer: C
The correct systemd.timer syntax is: bash OnCalendar=Mon *-2,5,8,11 13:30:00 This runs every Monday at 13:30 in the specified months. Reference:CompTIA Linux+ XK0-005 Study Guide, Domain 4.4 - Scheduled Tasks "Systemd timers use OnCalendar=DAY MONTH TIME syntax for scheduled tasks."