<< Prev Question Next Question >>

Question 5/31

A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (31q)
Question 1: During the execution phase of a project, a project task has ...
Question 2: Two team members are arguing over two different approaches t...
Question 3: A new project sponsor has joined the project team, and the c...
Question 4: Due to a new government regulation, a project change is requ...
Question 5: A project sponsor and Chief Information Officer (CIO) disagr...
Question 6: Which of the following activities are associated with the cl...
Question 7: Which of the following is a key aspect of the Agile project ...
Question 8: A vendor has accepted a proposed project from a customer. Wh...
Question 9: A company hires an outside vendor to provide 24/7 support. W...
Question 10: Which of the following is the MOST likely target audience to...
Question 11: A project manager is working on the project charter. Which o...
Question 12: Which of the following describes how a project is related to...
Question 13: Which of the following documents does a vendor rely on to co...
Question 14: A customer asks a project manager if a small change can be m...
Question 15: Which of the following is a schedule that illustrates the du...
Question 16: Which of the following individuals is MOST likely to be a ke...
Question 17: The project sponsor has cut the resources required for proje...
Question 18: A project team is composed of numerous team members who are ...
Question 19: The project manager for a TV tower construction project rece...
Question 20: The project manager has noticed a vendor is not performing i...
Question 21: Two team members have concluded that documentation is not re...
Question 22: After identifying all known tasks, the project manager has s...
Question 23: A project manager is managing a transactional project. One o...
Question 24: Which of the following are characteristics of a project? (Ch...
Question 25: Team members have reported that meetings are poorly attended...
Question 26: A project manager needs to identify the resources assigned t...
Question 27: A senior manager asks a project manager for an estimated bud...
Question 28: A project team is mainly based in a metropolitan area. The t...
Question 29: The key stakeholders have reported the project pace as being...
Question 30: During the execution phase, the project manager discovered t...
Question 31: A project has fallen behind schedule. Upon investigation, th...