A project manager is reviewing quality planning techniques. Which of the following involves comparing results of similar activities?
Correct Answer: C
Benchmarking is a quality technique that compares results, processes, or best practices from similar activities or organizations. It helps set realistic performance standards and identify improvement opportunities. Unlike cost-benefit analysis (financial), benchmarking focuses on performance comparison. Reference: CompTIA Project+ PK0-005 - Quality Planning Techniques; CompTIA Cloud+ CV0-004 Operations & Support domain.