<< Prev Question Next Question >>

Question 171/199

A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (199q)
Question 1: Which of the following shows projected project expenditures?...
Question 2: As a project processes, the team appears disjointed. Meeting...
Question 3: A project manager is assigned to an ongoing project. Which o...
Question 4: Which of the following are the components of a RACI matrix?...
Question 5: An engineer is troubleshooting a malfunctioning physical del...
Question 6: A company decides to give a large section of its development...
Question 7: Which of the following are examples of organizational change...
Question 8: In which of the following circumstances would faxing be the ...
Question 9: Which of the following captures unforeseen activities throug...
Question 10: The project manager has had a large number of change request...
Question 11: Which of the following charts would indicate the cause and e...
Question 12: A senior developer abruptly resigned without notice. Because...
Question 13: The project manager is reviewing the earned value of work co...
Question 14: A meeting has taken place with quality assurance tram member...
Question 15: An active project has a CPI of 0.92. Which of the following ...
Question 16: A customer has requested additional features for an active p...
Question 17: A company hires a number of interns and assigns them key rol...
Question 18: A project manager has received numerous complaints from staf...
Question 19: Two team members approach a project manager with different i...
Question 20: A number of requirements, conflicts, and reworks during a pr...
Question 21: A sports event is coming to a local city, and the project ma...
Question 22: When forming a project team, there are a number of phases. W...
Question 23: When an action is taken on a risk, which of the following is...
Question 24: A project manager is required to maintain various documents ...
Question 25: A project team has just finished one phase of product develo...
Question 26: The project manager needs to motivate the team; however, is ...
Question 27: A program manager informs a project manager that a new, high...
Question 28: A project manager wishes to track a project's performance ag...
Question 29: A milestone task on the critical path has been completed. Wh...
Question 30: A primary work location is unsafe due to a gas leak. The pro...
Question 31: A stakeholder with whom the project manager has worked on nu...
Question 32: A new project has just commenced. Project team members are c...
Question 33: A project is coming to the end of a phase. The PMO required ...
Question 34: A project has a BAC of $850,000. The project manager has ide...
Question 35: A project team is defining detailed risks. Which of the foll...
Question 36: A team member has completed an assigned task. Which of the f...
Question 37: Which of the following characteristics would stakeholders MO...
Question 38: Which of the following analyses should a project manager use...
Question 39: A new contractor joining the project team is an example of:...
Question 40: Which of the following risk management activities identifies...
Question 41: If a project sponsor wants to know the current status and pr...
Question 42: A team member was replaced on a project by a new team member...
Question 43: A project team on a four-year project has a shortage of work...
Question 44: A project sponsor approved an undocumented change without fo...
Question 45: A project has fallen behind schedule. Upon investigation, th...
Question 46: Which of the following are MOST likely the responsibilities ...
Question 47: A project has just finished performance testing and found th...
Question 48: A project manager is informed that a team member would like ...
Question 49: One deliverable failed during testing, and this has already ...
Question 50: Which of the following should be included in an effective SO...
Question 51: A daily standup Scrum meeting is BEST accomplished in a:...
Question 52: There is a project in which the team can only meet once ever...
Question 53: A project manager receives a call from the area regional bui...
Question 54: Which of the following is the primary purpose of an MOA or a...
Question 55: Two team members are arguing over two different approaches t...
Question 56: A project manager has been experiencing resistance from a gr...
Question 57: A project manager has been asked to prepare and present a re...
Question 58: The PM has requested that a project repository be developed....
Question 59: Which of the following project management roles is responsib...
Question 60: A project manager learns that a key team member is required ...
Question 61: During an ad-hoc meeting, the OM notifies the sponsor that w...
Question 62: The project team is not comfortable moving an expensive mate...
Question 63: An authorized change to a construction project was implement...
Question 64: Which of the following documents is typically signed by the ...
Question 65: A project team has determined it will need to source data fr...
Question 66: Which of the following documents need to be updated as event...
Question 67: A project manager is assigned to a project with an unfamilia...
Question 68: Which of the following is the BEST method to provide quick s...
Question 69: At a weekly project team meeting, it is apparent the project...
Question 70: During the planning phase of a construction project, the pro...
Question 71: A project manager is analyzing the cost variances produced w...
Question 72: Given the following sprint: (Exhibit) Which of the following...
Question 73: Three IT companies have agreed to summarize their efforts as...
Question 74: In a project with a BAC of $235,000, the CPI is 0.80, and th...
Question 75: A project coordinator notices there is a scheduling conflict...
Question 76: A project manager receives an initial project assignment. Wh...
Question 77: An employee is assigned to a project and is developing a pro...
Question 78: There are four parallel paths on a network diagram. The summ...
Question 79: A project manager is justifying a required change with the a...
Question 80: Which of the following organization types requires the proje...
Question 81: A project sponsor has requested documentation to determine t...
Question 82: A project has passed a phase-gate, and the new phase is read...
Question 83: Which of the following events would MOST likely trigger comm...
Question 84: The project team has identified all the tasks needed to crea...
Question 85: A project team is not delivering their tasks in a timely man...
Question 86: A project schedule lists a resource as 50% because it likely...
Question 87: A resource is assigned to two projects with two scheduled ta...
Question 88: Assuming an iterative approach, which of the following will ...
Question 89: Which of the following tasks are responsibilities of the pro...
Question 90: During a project, a key stakeholder asks a project team memb...
Question 91: The anticipated funding level for an approved project was re...
Question 92: A new project manager is working in an environment where res...
Question 93: Which of the following make up a company's portfolio? (Choos...
Question 94: A new corporate policy was approved that will positively aff...
Question 95: Which of the following are characteristics of qualitative ri...
Question 96: Two highly skilled resources, who are currently working on o...
Question 97: Using Scrum, which of the following are discussed in a daily...
Question 98: Which of the following describes the difference between an a...
Question 99: Which of the following is a schedule that illustrates the du...
Question 100: In which of the following organizational structures would a ...
Question 101: Two team members completely disagree on how to complete a sp...
Question 102: Which of the following activities are associated with the cl...
Question 103: Project cost control deals with:...
Question 104: A key stakeholder asked several members of the project team ...
Question 105: On larger projects, a vendor may occasionally proceed upon r...
Question 106: Which of the following project management tools provides an ...
Question 107: A local company is part of a hostile takeover by a multinati...
Question 108: A client has requested a project be completed ahead of sched...
Question 109: The chairperson of the board is visiting from another countr...
Question 110: A project has just begun, and people are not clear about the...
Question 111: During planning, a project coordinator publishes the project...
Question 112: A project manager is working on a project, which needs to be...
Question 113: Which of the following describes how a project is related to...
Question 114: A change must be made to a project to comply with municipal ...
Question 115: Which of the following metrics are used to determine a proje...
Question 116: Which of the following vendor documents specifically address...
Question 117: Given the information in the table below, which of the follo...
Question 118: A project manager is archiving of project documents. Which o...
Question 119: A project manager is not going to finish a project on time b...
Question 120: A company recently went through a project requiring new equi...
Question 121: During the risk assessment process, the qualitative analysis...
Question 122: Based on the table below: (Exhibit) Which of the following i...
Question 123: A change is being implemented on a project, and while in tes...
Question 124: Project B cannot start before Project A is complete, but Pro...
Question 125: Which of the following information does the project risk reg...
Question 126: A company recently discovered that it could save money by mo...
Question 127: Which of the following individuals is MOST likely to be a ke...
Question 128: Which of the following elements should be included on a resp...
Question 129: Which of the following defines the minimum level of engageme...
Question 130: The project manager of a global project constantly receives ...
Question 131: A project manager is assigned a project that is part of the ...
Question 132: A project sponsor wants to know when the plan changed to shi...
Question 133: Communication on a project is flowing well. Team members are...
Question 134: Which of the following documents ensures two parties do not ...
Question 135: A project is moving into the next phase, and those involved ...
Question 136: A project manager is planning to hold a meeting to discuss w...
Question 137: When a risk event occurs, which of the following documents i...
Question 138: Which of the following can a project manager use to keep tra...
Question 139: Because of space limitations, there has been a long history ...
Question 140: The project sponsor has cut the resources required for proje...
Question 141: Which of the following are the roles involved in a Scrum pro...
Question 142: An American publisher is participating in a workshop in Hong...
Question 143: A project manager is releasing resources and archiving docum...
Question 144: A project sponsor and Chief Information Officer (CIO) disagr...
Question 145: Which of the following is a definition of an RFP?...
Question 146: The key stakeholders have reported the project pace as being...
Question 147: At that will result in minor changes to the project budget a...
Question 148: A project manager at a projectized organization is resource ...
Question 149: A project's key stakeholders have requested significant chan...
Question 150: Several team members report that meeting objectives are not ...
Question 151: Rather than sending emails to communicate all project inform...
Question 152: A project manager was directed to complete a project sooner ...
Question 153: A project manager has been assigned a complex project and do...
Question 154: A project manager noticed the development team supporting a ...
Question 155: A firm, fixed-price project is on pace to exceed the maximum...
Question 156: A project manager is implementing a new edition of a magazin...
Question 157: The project manager was asked to provide recommendations for...
Question 158: Team members in a projectized organization are released at t...
Question 159: A project manager received a change request, immediately doc...
Question 160: A company has determined it does not have the in-house capab...
Question 161: A company has dictated project scope changes but has stated ...
Question 162: A customer asks a project manager if a small change can be m...
Question 163: During a risk review session, the project team identified th...
Question 164: Which of the following documents is a snapshot in time of a ...
Question 165: An organization is divided into three separate entities base...
Question 166: A project team is comprised of a mix of in-house and virtual...
Question 167: A team lead informs the project manager that the datacenter ...
Question 168: A project team member states that the tasks identified in th...
Question 169: Which of the following features describe a projectized organ...
Question 170: A new project manager is assigned in the middle of a seven-m...
Question 171: A project manager at a projectized organization is finishing...
Question 172: Task ID 3 did not start on time, and no work has been accomp...
Question 173: As part of the early stages of a potential corporate acquisi...
Question 174: A project manager is collecting the number of hours, the res...
Question 175: A project sponsor wants to know which tasks are next in the ...
Question 176: The project schedule performance index is 1.1, and the cost ...
Question 177: In the review of a project status report, the slack is negat...
Question 178: Which of the following includes setting governance gates as ...
Question 179: A solid line is connecting a project team member to two peop...
Question 180: A project manager needs status on the project timeline. Whic...
Question 181: The executive sponsor asks a project manager to summarize th...
Question 182: A customer has stated that meeting the project schedule and ...
Question 183: Based on the table below: (Exhibit) Which of the following i...
Question 184: A project team has completed a major deliverable earlier tha...
Question 185: The project team is moving from high-level risks to detailed...
Question 186: A project manager has an opportunity to add a highly skilled...
Question 187: A project manager has gathered time estimates for a new proj...
Question 188: In a projectized organization, a project manager has a need ...
Question 189: A new stakeholder has requested the status and progress repo...
Question 190: A sprint retrospective is being conducted. Which of the foll...
Question 191: A project can be defined as:
Question 192: A project team has purchased computers with warranties exten...
Question 193: Which of the following is a risk strategy?...
Question 194: A critical issue has developed in an active project, and the...
Question 195: A Chief Executive Officer (CEO) has approached a project tea...
Question 196: The Chief Executive Officer (CEO) of a company announced tha...
Question 197: On an OBS chart, there is a dashed line between some team me...
Question 198: A project team is mainly based in a metropolitan are a. The ...
Question 199: A company has updated the method it uses to initiate project...