Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question

Question 176/176

A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (176q)
Question 1: Which of the following would indicate a project manager is w...
Question 2: An organization has multiple projects that are taking place ...
Question 3: A project can be defined as:
Question 4: Which of the following communication methods and target audi...
Question 5: In a Scrum retrospective, which of the following categories ...
Question 6: An active construction project must make immediate changes w...
Question 7: After SOW and contract approvals, the project manager plans ...
Question 8: A company recently discovered that it could save money by mo...
Question 9: A critical issue has developed in an active project, and the...
Question 10: A project manager is assigned to an ongoing project. Which o...
Question 11: A developer is experiencing constant project scope changes a...
Question 12: Which of the following documents is typically signed by the ...
Question 13: A company has dictated project scope changes but has stated ...
Question 14: A project manager is managing a transactional project. One o...
Question 15: A financial audit is being performed on a closed project. Wh...
Question 16: A fire occurred in the production facility over the weekend,...
Question 17: A company is in the process of combining the human resources...
Question 18: During a CCB, a SME evaluated the impact and provided new in...
Question 19: A new project has just commenced. Project team members are c...
Question 20: Communication on a project is flowing well. Team members are...
Question 21: Which of the following Agile ceremonies is used to determine...
Question 22: A project is about to begin the execution phase. The SOW and...
Question 23: A project manager does not have enough time to complete seve...
Question 24: Due to a lack of adherence to the risk response plan, there ...
Question 25: The project manager needs to motivate the team; however, is ...
Question 26: Which of the following statements are correct regarding proj...
Question 27: There are four parallel paths on a network diagram. The summ...
Question 28: The internal project sponsor is frustrated by a lack of conc...
Question 29: Which of the following is a team-building stage that involve...
Question 30: Expenditure tracking helps with cost:...
Question 31: A project manager is mapping qualifications and available pe...
Question 32: After identifying all known tasks, the project manager has s...
Question 33: A project manager is planning to hold a meeting to discuss w...
Question 34: A project manager is assigned a project that is part of the ...
Question 35: Which of the following documents need to be updated as event...
Question 36: A project manager has received a change order that will redu...
Question 37: The PMO is responsible for: (Choose two.)...
Question 38: An active project is focused on quality assurance of the del...
Question 39: An authorized change to a construction project was implement...
Question 40: Which of the following documents serves the primary purpose ...
Question 41: A PM receives notification that an issue will impact a deliv...
Question 42: Which of the following is the MOST appropriate communication...
Question 43: A PM notes a feature that was delivered does not appear in t...
Question 44: A project manager, who previously worked at a construction f...
Question 45: A project coordinator notices there is a scheduling conflict...
Question 46: During a project assessment, a project manager determines th...
Question 47: Which of the following charts would indicate the cause and e...
Question 48: A project team added a new member who has proprietary inform...
Question 49: The project team is not comfortable moving an expensive mate...
Question 50: A risk with minor impact has been realized. There is no chan...
Question 51: Which of the following are major characteristics of sprint p...
Question 52: A small company has a successful proof of concept for an inn...
Question 53: A Chief Executive Officer (CEO) has approached a project tea...
Question 54: A post implementation review is being performed as a part of...
Question 55: The project manager for a TV tower construction project rece...
Question 56: In the review of a project status report, the slack is negat...
Question 57: A project sponsor wants to demonstrate progress on a deliver...
Question 58: Which of the following resources outlines consequences of no...
Question 59: A company was originally organized using a functional struct...
Question 60: A vendor is unable to deliver an order by the specified date...
Question 61: Which of the following is the BEST reason to conduct regular...
Question 62: As a project processes, the team appears disjointed. Meeting...
Question 63: Which of the following is the primary purpose of an MOA or a...
Question 64: A project manager wishes to track a project's performance ag...
Question 65: A team member has reported Task 3 will be completed ahead of...
Question 66: Which of the following organization types requires the proje...
Question 67: The project manager is running a project in an organization ...
Question 68: If a project sponsor wants to know the current status and pr...
Question 69: Before a team can start on a sprint, they will need to:...
Question 70: A vendor was removed from a company due to non-performance b...
Question 71: Ann, one of the affected stakeholders, feels that the projec...
Question 72: Which of the following project phases occurs when requiremen...
Question 73: A project has fallen behind schedule. Upon investigation, th...
Question 74: Based on the table below: (Exhibit) Which of the following i...
Question 75: A company recently went through a project requiring new equi...
Question 76: A key stakeholder cannot identify within the resource manage...
Question 77: A project team received a memo stating no one can come into ...
Question 78: Which of the following is a schedule that illustrates the du...
Question 79: Language barriers will MOST likely influence a PM to:...
Question 80: Which of the following represents additional unauthorized re...
Question 81: Which of the following risk strategies is represented by the...
Question 82: A project manager is collecting the number of hours, the res...
Question 83: A vendor has accepted a proposed project from a customer. Wh...
Question 84: A project is coming to the end of a phase. The PMO required ...
Question 85: The project manager was asked to provide recommendations for...
Question 86: Which of the following is an example of a project?...
Question 87: A project team member states that the tasks identified in th...
Question 88: A project manager must create documentation before the proje...
Question 89: A project has a BAC of $850,000. The project manager has ide...
Question 90: Which of the following job roles is MOST responsible for pro...
Question 91: A milestone task on the critical path has been completed. Wh...
Question 92: Which of the following describes risk mitigation?...
Question 93: A new high-priority project is assigned to the project manag...
Question 94: A project's key stakeholders have requested significant chan...
Question 95: A part that is needed to complete Task 3 has been backordere...
Question 96: A project manager at a projectized organization is finishing...
Question 97: The project's network map has a loop with multiple project o...
Question 98: A project sponsor, project manager, and project facilitator ...
Question 99: Ann, a project manager, is working for a new company. On her...
Question 100: During the testing phase, a team member has informed the pro...
Question 101: The PMO is confused by an entry in the risk register and wou...
Question 102: A project manager is informed that a team member would like ...
Question 103: An organization is divided into three separate entities base...
Question 104: At a weekly project team meeting, it is apparent the project...
Question 105: A project manager is starting a project on an unfamiliar tec...
Question 106: The executive sponsor asks a project manager to summarize th...
Question 107: A project team has purchased computers with warranties exten...
Question 108: A new corporate policy was approved that will positively aff...
Question 109: A new contractor joining the project team is an example of:...
Question 110: A project team is spread between two countries on different ...
Question 111: The government wants to start a project that will launch a s...
Question 112: An organization wants assurance that the specialty tools nec...
Question 113: A project manager is working on the project charter. Which o...
Question 114: A PM is asked to keep the Chief Information Officer (CIO) in...
Question 115: A project manager is successfully adhering to an eight-week ...
Question 116: A stakeholder with whom the project manager has worked on nu...
Question 117: Tasks A and B have a duration of two days. Task A starts on ...
Question 118: A project manager who is part of a global team wants to have...
Question 119: The Chief Executive Officer (CEO) of a company announced tha...
Question 120: A project manager is performing resource leveling and notice...
Question 121: Gas prices were included in the cost baseline for a transpor...
Question 122: A project manager is justifying a required change with the a...
Question 123: The project sponsor has cut the resources required for proje...
Question 124: A client has provided a list of deliverables to include in t...
Question 125: A PM is reviewing bids from vendors and has a question. Whic...
Question 126: A project manager is creating the WBS. In which of the follo...
Question 127: A business has implemented a new online performance manageme...
Question 128: Which of the following documents are considered mutually bin...
Question 129: A project manager is attempting to establish the proper sequ...
Question 130: A company is hired to perform some of another organization's...
Question 131: Which of the following activities are associated with the cl...
Question 132: A subcontractor has submitted design documentation on the de...
Question 133: A hurricane occurs in an area where several key project reso...
Question 134: An audit, project change, task initiation/completion, gate r...
Question 135: A non-stakeholder approaches the project manager and asks if...
Question 136: An industry leader may be joining the project team and can p...
Question 137: Two parties are beginning conversations regarding the purcha...
Question 138: Which of the following documents does a vendor rely on MOST ...
Question 139: A senior developer abruptly resigned without notice. Because...
Question 140: A project manager has contracted a third-party vendor to ach...
Question 141: A project team has finished creating a WBS and started devel...
Question 142: A change is being implemented on a project, and while in tes...
Question 143: A customer has requested additional features for an active p...
Question 144: A project manager is reviewing project performance. Which of...
Question 145: When closing a project, which of the following must be compl...
Question 146: Which of the following roles is MOST involved in checking th...
Question 147: Which of the following is the MOST likely target audience to...
Question 148: A new stakeholder has been added to a project with a BAG of ...
Question 149: A task on the critical path will not be completed on time. T...
Question 150: A software upgrade project has been postponed because it may...
Question 151: Which of the following describes the difference between an a...
Question 152: A project is running behind schedule. To meet the delivery t...
Question 153: Which of the following documents should be used FIRST when a...
Question 154: Two team members have concluded that documentation is not re...
Question 155: A project team has failed to deliver on changes the project ...
Question 156: The project manager has noticed a vendor is not performing i...
Question 157: A project team has determined it will need to source data fr...
Question 158: Which of the following charts is a mathematical diagram used...
Question 159: When forming a project team, there are a number of phases. W...
Question 160: Which of the following project phases would MOST likely incl...
Question 161: A key stakeholder claims to have not received status updates...
Question 162: An engineer is troubleshooting a malfunctioning physical del...
Question 163: A project manager is releasing resources and archiving docum...
Question 164: The quarterly financial statement has been released, and por...
Question 165: An organization needs a vendor to provide a solution. The or...
Question 166: A key stakeholder asks the project manager for additional fe...
Question 167: During the initiation phase, a project manager has asked for...
Question 168: A project has fallen behind schedule for no obvious reason, ...
Question 169: The key stakeholders have reported the project pace as being...
Question 170: During the execution phase, the project manager discovered t...
Question 171: A project manager has noticed poor attendance as status meet...
Question 172: The Chief Executive Officer (CEO) has changed the direction ...
Question 173: Which of the following is the first document issued during t...
Question 174: Two team members completely disagree on how to complete a sp...
Question 175: A project manager is assigned to a new project that must sta...
Question 176: A task on the critical path has just been completed. The pro...