A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter: * Project title description * Preassigned resources * Budget * WBS * Measurable project objectives Which of the following components should be a part of the project management plan instead of the project charter?