Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?
Correct Answer: A
Explanation/Reference: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 233