Valid N10-009 Dumps shared by EduDump.com for Helping Passing N10-009 Exam! EduDump.com now offer the newest N10-009 exam dumps, the EduDump.com N10-009 exam questions have been updated and answers have been corrected get the newest EduDump.com N10-009 dumps with Test Engine here:
After extremely high temperatures cause a power outage, the servers automatically shut down, even though the UPSs for the servers still have hours of battery life. Which of the following should a technician recommend?
Correct Answer: A
Servers shut down due to overheating, not loss of electrical power. Although UPS units had battery life, without cooling systems (HVAC/air conditioning) running on backup power, server rooms overheated. Backup power for air-conditioning is essential in data center design. B). Door locks are unrelated to server shutdown. C). Increasing UPS capacity won't help cooling. D). IoT thermostats may monitor temperature but won't prevent overheating. References (CompTIA Network+ N10-009): Domain: Network Infrastructure - Environmental controls, power redundancy, HVAC systems.